What does RACI stand for?
Suggested Answer: D Vote an answer
RACI is a project management and governance framework used to define roles and responsibilities within a project. Each letter represents a distinct role type:
Responsible (R): The person(s) who perform the work or execute the task.
Accountable (A): The individual ultimately answerable for the task's completion and success (only one per activity).
Consulted (C): Subject matter experts who provide input or guidance before decisions are made.
Informed (I): Individuals kept up to date on progress or outcomes but not directly involved in execution.
The RACI model ensures clarity in ownership and accountability, preventing duplication of effort or responsibility confusion. It is a key component of the GCDMP (Chapter: Project Management in Data Management) for ensuring clear delegation and communication within clinical data management teams.
Hence, option D is correct.
Reference (CCDM-Verified Sources):
SCDM GCDMP, Chapter: Project Management in Data Management, Section 5.1 - Roles, Responsibilities, and RACI Matrices Project Management Institute (PMI) Framework - Responsibility Assignment Matrices (RACI) ICH E6(R2) GCP, Section 5.1.1 - Defined Roles and Quality Oversight Responsibilities
Responsible (R): The person(s) who perform the work or execute the task.
Accountable (A): The individual ultimately answerable for the task's completion and success (only one per activity).
Consulted (C): Subject matter experts who provide input or guidance before decisions are made.
Informed (I): Individuals kept up to date on progress or outcomes but not directly involved in execution.
The RACI model ensures clarity in ownership and accountability, preventing duplication of effort or responsibility confusion. It is a key component of the GCDMP (Chapter: Project Management in Data Management) for ensuring clear delegation and communication within clinical data management teams.
Hence, option D is correct.
Reference (CCDM-Verified Sources):
SCDM GCDMP, Chapter: Project Management in Data Management, Section 5.1 - Roles, Responsibilities, and RACI Matrices Project Management Institute (PMI) Framework - Responsibility Assignment Matrices (RACI) ICH E6(R2) GCP, Section 5.1.1 - Defined Roles and Quality Oversight Responsibilities
by Borg at Mar 04, 2026, 01:15 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).