Exam Development-Lifecycle-and-Deployment-Architect Topic 8 Question 228 Discussion
Actual exam question for Salesforce's Development-Lifecycle-and-Deployment-Architect exam
Question #: 228
Topic #: 8
Question #: 228
Topic #: 8
Universal Containers is in the final stages of building a new application to track custom containers. During a review of the application, a business subject Matter Expert mentioned that it would be nice to be able to track additional container types beyond what was originally scoped during the plan and design phase. Which two actions should be performed to mitigate the risk? Choose 2 answers.
Suggested Answer: A,C Vote an answer
Escalating and communicating to stakeholders the risk and mitigating it by allocating additional resources or extending the timeline of the project to support the new requirement based on stakeholders' input are two actions that should be performed to mitigate the risk. These actions help to manage the scope change and ensure that the project is delivered with the expected quality and functionality.
by Miriam at Jul 02, 2026, 03:37 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).