What is one accountability of a Scrum Master?
Suggested Answer: C Vote an answer
One of the key accountabilities of aScrum Masteris toimprove the Scrum Team's effectiveness. This aligns with the Scrum Master's role as a servant leader who helps the team deliver value through better practices, collaboration, and adherence to Scrum principles.
According to the2020 Scrum Guide, the Scrum Master is accountable for:
* Establishing Scrum as defined in the Scrum Guide, helping everyone understand its theory and practices.
* Improving the Scrum Team's effectivenessby enabling the team to self-manage, improve cross- functionality, and focus on delivering high-value Increments.
* Removing impedimentsthat hinder progress and supporting the team in achieving its Sprint Goals.
Why the other options are incorrect:
* A. Set the budget:The Scrum Master does not manage budgets. Budgeting decisions are outside the scope of the Scrum framework.
* B. Provide estimates:Developers are responsible for providing estimates during Product Backlog refinement and Sprint Planning.
* D. Decide when to release the product:Decisions about releases are made collaboratively by the Product Owner, often based on business needs and stakeholder input.
According to the2020 Scrum Guide, the Scrum Master is accountable for:
* Establishing Scrum as defined in the Scrum Guide, helping everyone understand its theory and practices.
* Improving the Scrum Team's effectivenessby enabling the team to self-manage, improve cross- functionality, and focus on delivering high-value Increments.
* Removing impedimentsthat hinder progress and supporting the team in achieving its Sprint Goals.
Why the other options are incorrect:
* A. Set the budget:The Scrum Master does not manage budgets. Budgeting decisions are outside the scope of the Scrum framework.
* B. Provide estimates:Developers are responsible for providing estimates during Product Backlog refinement and Sprint Planning.
* D. Decide when to release the product:Decisions about releases are made collaboratively by the Product Owner, often based on business needs and stakeholder input.
by Dawn at Jun 23, 2026, 01:29 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).