How much time must a product owner spend with the developers?
Suggested Answer: A Vote an answer
This should not be too much in a healthy situation, and this also doesn't imply that the developers can control the PO. But when the developers need the product owner to clarify or renegotiate the work to be done, it will be an impediment if the PO is not available.