Exam PSM-I Topic 1 Question 113 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 113
Topic #: 1
During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

Suggested Answer: B Vote an answer

The correct answer is B, because the Scrum Guide states that "the Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal." Therefore, new work or further decomposition of work can be added to the Sprint Backlog as soon as possible after they are identified by the Development Team.

by Adrian at Jan 25, 2025, 05:39 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10