Exam PSM-I Topic 1 Question 265 Discussion
Actual exam question for Scrum's PSM-I exam
Question #: 265
Topic #: 1
Question #: 265
Topic #: 1
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities.
Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
Suggested Answer: C,D Vote an answer
by Marguerite at Apr 21, 2026, 03:50 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.