Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Suggested Answer: B Vote an answer
The correct answer is B, because the Scrum Guide states that "the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Development Team on why it is building the Increment." Therefore, the Sprint Goal provides the Development Team with a target and overarching direction for the Sprint.