Exam PSM-I Topic 2 Question 139 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 139
Topic #: 2
How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

Suggested Answer: B Vote an answer

The correct answer is B, because when multiple Scrum Teams work from the same Product Backlog, they should pull in work in agreement with the Product Owner. The Scrum Guide states that "multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of 'Done' that applies to their combined work product." Therefore, they should collaborate and coordinate with each other and with the Product Owner to select Product Backlog items that align with their shared product goal.

by Zoe at Aug 01, 2025, 12:21 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10