Exam PSM-I Topic 2 Question 223 Discussion
Actual exam question for Scrum's PSM-I exam
Question #: 223
Topic #: 2
Question #: 223
Topic #: 2
What is the timebox for the Sprint Planning event? (Choose the best answer.)
Suggested Answer: C Vote an answer
The correct answer is C because Sprint Planning is timeboxed to a maximum of eight hours for a one- month Sprint. For shorter Sprints, the event is usually shorter. This timebox is defined in the Scrum Guide and helps ensure that planning is focused, efficient, and proportionate to the length of the Sprint.
Sprint Planning starts the Sprint by setting a clear direction for the work ahead. During this event, the Scrum Team discusses why the Sprint is valuable, what can be done during the Sprint, and how the chosen work will be accomplished. The outcome is the Sprint Goal, the selected Product Backlog items, and the initial Sprint Backlog plan.
Sprint Planning starts the Sprint by setting a clear direction for the work ahead. During this event, the Scrum Team discusses why the Sprint is valuable, what can be done during the Sprint, and how the chosen work will be accomplished. The outcome is the Sprint Goal, the selected Product Backlog items, and the initial Sprint Backlog plan.
by Adonis at Jul 09, 2026, 05:25 AM