Exam PSM-I Topic 2 Question 223 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 223
Topic #: 2
What is the timebox for the Sprint Planning event? (Choose the best answer.)

Suggested Answer: C Vote an answer

The correct answer is C because Sprint Planning is timeboxed to a maximum of eight hours for a one- month Sprint. For shorter Sprints, the event is usually shorter. This timebox is defined in the Scrum Guide and helps ensure that planning is focused, efficient, and proportionate to the length of the Sprint.
Sprint Planning starts the Sprint by setting a clear direction for the work ahead. During this event, the Scrum Team discusses why the Sprint is valuable, what can be done during the Sprint, and how the chosen work will be accomplished. The outcome is the Sprint Goal, the selected Product Backlog items, and the initial Sprint Backlog plan.

by Adonis at Jul 09, 2026, 05:25 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10