Exam PSM-I Topic 2 Question 251 Discussion
Actual exam question for Scrum's PSM-I exam
Question #: 251
Topic #: 2
Question #: 251
Topic #: 2
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
A good way to continue is:
Suggested Answer: A Vote an answer