Exam PSM-I Topic 3 Question 187 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 187
Topic #: 3
When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint' (choose the best answer)

Suggested Answer: B Vote an answer

According to the Scrum Guide, a Developer becomes accountable for the value of a Product Backlog item selected for the Sprint at the Sprint Planning event. This is when the Developers select items from the Product Backlog that they can commit to complete within a Sprint. The Developers are then responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they either imply that Developers are not accountable for value (such as never or whenever), or that they become accountable at a different time (such as during the Daily Scrum).

by MW at Aug 05, 2024, 12:44 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
MW
2024-08-05 00:44:53
Selected Answer: A
All members of the Scrum Team share in the accountability for creating value every Sprint.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.