A Sprint Retrospective should be held:
Suggested Answer: A Vote an answer
The correct answer is A, because a Sprint Retrospective should be held at the end of each Sprint. The Scrum Guide states that "the Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. ... The Sprint Retrospective occurs after the Sprint Review and prior to the next Sprint Planning."