Exam PSM-II Topic 1 Question 136 Discussion

Actual exam question for Scrum's PSM-II exam
Question #: 136
Topic #: 1
During Sprint Planning, the Definition of Done will help the Development Team forecast the amount of work, selected from the Product Backlog, deemed feasible to make `done' by the end of the Sprint.
Which two items best describes what `done' means? (Choose two.)

Suggested Answer: C,D Vote an answer

When a Product Backlog item or an Increment is described as `Done', everyone must understand what `Done' means. Although this may vary significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and is used to assess when work is complete on the product Increment. The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the Scrum Team's current Definition of Done.

by Mick at Oct 14, 2026, 01:50 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10