Exam PSM-II Topic 1 Question 19 Discussion
Actual exam question for Scrum's PSM-II exam
Question #: 19
Topic #: 1
Question #: 19
Topic #: 1
A new Product Owner has joined an existing Scrum Team that has been working together for eight Sprints. The Development Team has grown to have a good understanding of the functionality and business for the product they have been building. The Product Owner, being new to the company, is unsure about his responsibilities.
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)
Suggested Answer: A,D Vote an answer
The ones that are closest to the work are the best ones to understand and explain what the work is and what the needs of the users and product are.
by Eleanore at Jan 28, 2026, 10:21 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).