True or False: Multiple Scrum Teams working on the same product must have the same Sprint start date.

Suggested Answer: B Vote an answer

Explanation
Multiple Scrum Teams working on the same product do not have to have the same Sprint start date. The Scrum Guide does not prescribe any synchronization of Sprints across multiple teams1. However, it is recommended that the teams align their Sprint cadence and duration, and coordinate their dependencies and integration through a shared Product Backlog, a common Definition of Done, and frequent communication2.
This way, the teams can deliver a coherent and valuable product Increment every Sprint[3][3].
References:
1: The Scrum Guide, November 2020, p. 9
2: Managing Products with Agility, Scrum.org, accessed on December 16, 2023
[3][3]: Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023

by Webb at Nov 26, 2025, 09:56 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10