Which ADM Phase provides architectural oversight of the implementation?
Suggested Answer: A Vote an answer
* Phase G: Implementation Governance provides architectural oversight of the implementation. It ensures that the implementation conforms to the Target Architecture using Architecture Contracts and governance frameworks.
* Phase H: Architecture Change Management is about maintaining the architecture lifecycle and handling new requirements, not direct implementation oversight.
* Preliminary Phase is about setting up the architecture capability.
* Phase A is about developing the Architecture Vision.
Reference: TOGAF Standard, Version 9.2, Part II: ADM, Phase G.
* Phase H: Architecture Change Management is about maintaining the architecture lifecycle and handling new requirements, not direct implementation oversight.
* Preliminary Phase is about setting up the architecture capability.
* Phase A is about developing the Architecture Vision.
Reference: TOGAF Standard, Version 9.2, Part II: ADM, Phase G.
by Clifford at Jun 10, 2026, 03:19 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).