CompTIA.PK0-004.v2019-11-07.q100

Exam Code:PK0-004
Exam Name:CompTIA Project+ Exam
Certification Provider:CompTIA
Free Question Number:100
Version:v2019-11-07
Rating:
# of views:138
# of Questions views:1236
Start Practice Test

Valid PK0-004 Dumps shared by PrepAwayExam.com for Helping Passing PK0-004 Exam! PrepAwayExam.com now offer the newest PK0-004 exam dumps, the PrepAwayExam.com PK0-004 exam questions have been updated and answers have been corrected get the newest PrepAwayExam.com PK0-004 dumps with Test Engine here:

Access Premium Version
(322 Q&As Dumps, 40%OFF Special Discount: freecram)

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
392 viewsCompTIA.PK0-004.v2018-11-12.q118
Exam Question List
Question 1: A new corporate policy was approved that will positively aff...
Question 2: A new stakeholder has requested the status and progress repo...
Question 3: During a project, a key stakeholder asks a project team memb...
Question 4: A project is about to begin the execution phase. The SOW and...
Question 5: Which of the following elements should be included on a resp...
Question 6: Which of the following is the MOST appropriate communication...
Question 7: A project manager has contracted a third-party vendor to ach...
Question 8: A project team is defining detailed risks. Which of the foll...
Question 9: A project team member highlights to the project manager that...
Question 10: Project status meetings have poor attendance. A SME from the...
Question 11: Which of the following describes a burn rate?...
Question 12: A project manager is trying to explain to a stakeholder why ...
Question 13: A governance committee has just approved a new project. The ...
Question 14: The project team is distributed throughout a single country....
Question 15: A minor change to the baseline schedule is required. This ch...
Question 16: A vendor was removed from a company due to non-performance b...
Question 17: Which of the following shows projected project expenditures?...
Question 18: A daily standup Scrum meeting is BEST accomplished in a:...
Question 19: Which of the following documents serves the primary purpose ...
Question 20: A change is being implemented on a project, and while in tes...
Question 21: A team member has completed an assigned task. Which of the f...
Question 22: Which of the following activity sequencing techniques uses n...
Question 23: A project manager is justifying a required change with the a...
Question 24: A project manager has an opportunity to add a highly skilled...
Question 25: During the execution phase of a project, a project task has ...
Question 26: A project manager is reviewing documents to develop the proj...
Question 27: An organization needs a vendor to provide a solution. The or...
Question 28: Which of the following analyses should a project manager use...
Question 29: An organization has determined that all projects must use a ...
Question 30: Which of the following information does the project risk reg...
Question 31: A senior developer abruptly resigned without notice. Because...
Question 32: A software development project is struggling with a certain ...
Question 33: When closing a project, which of the following must be compl...
Question 34: A new project charter is being drafted. Which of the followi...
Question 35: A project manager has developed the initial schedule for an ...
Question 36: During the storming stage of a project team's development, i...
Question 37: The key stakeholders have reported the project pace as being...
Question 38: Despite receiving regular updates, a sponsor learns a projec...
Question 39: When an action is taken on a risk, which of the following is...
Question 40: Which of the following documents need to be updated as event...
Question 41: Two team members are arguing over two different approaches t...
Question 42: A PM receives notification that an issue will impact a deliv...
Question 43: A project team is spread between two countries on different ...
Question 44: A company has updated the method it uses to initiate project...
Question 45: A project has a of $850,000. The project manager has identif...
Question 46: A project manager receives a call from the area regional bui...
Question 47: A project manager has been assigned a project with a budget ...
Question 48: A project is coming to the end of a phase. The PMO requires ...
Question 49: Which of the following is a schedule that illustrates the du...
Question 50: During a project, the project manager discovers there is ins...
Question 51: A company hires a number of interns and assigns them key rol...
Question 52: The project sponsor has cut the resources required for proje...
Question 53: A project manager is trying to ensure the quality of the des...
Question 54: Which of the following techniques modifies the schedule base...
Question 55: A project team has purchased computers with warranties exten...
Question 56: Which of the following conflict resolution techniques relies...
Question 57: A project manager is meeting with top management executives ...
Question 58: Which of the following is the primary purpose of an MOA or a...
Question 59: A project manager procures additional resources from a local...
Question 60: A diagram or chart is required to illustrate data difference...
Question 61: A project manager has received numerous complaints from staf...
Question 62: Which of the following is a team-building stage that involve...
Question 63: A quality auditor finds suspicious code during a software te...
Question 64: The project's network map has a loop with multiple project o...
Question 65: A risk with minor impact has been realized. There is no chan...
Question 66: A project team on a four-year project has a shortage of work...
Question 67: A stakeholders asked for a change to the project. The projec...
Question 68: A company has dictated project scope changes but has stated ...
Question 69: The executive sponsor asks a project manager to summarize th...
Question 70: Two companies have merged. Which of the following may impact...
Question 71: Which of the following describes risk mitigation?...
Question 72: Which of the following is used to perform a root cause analy...
Question 73: A team has been assembled and assigned a project to reduce r...
Question 74: Which of the following describes how a project is related to...
Question 75: Using Scrum, which of the following are discussed in a daily...
Question 76: A project manager is informed that a team member would like ...
Question 77: At a project kickoff meeting, several team members acted unp...
Question 78: A risk with a high probability and medium consequence to a p...
Question 79: Under an Agile methodology, standup meetings occur:...
Question 80: During the planning phase of a construction project, the pro...
Question 81: Which of the following inherently affects quality standards?...
Question 82: On an OBS chart, there is a dashed line between some team me...
Question 83: The project manager of a global project constantly receives ...
Question 84: A project manager is unsure if the quality of a deliverable ...
Question 85: Which of the following Agile ceremonies is used to determine...
Question 86: An industry leader may be joining the project team and can p...
Question 87: Which of the following are examples of organizational change...
Question 88: A stakeholder is unaware of a project's status. Which of the...
Question 89: A project manager has received a change order that will redu...
Question 90: The chairperson of the board is visiting from another countr...
Question 91: The PM is preparing for the planning phase kickoff meeting. ...
Question 92: A manufacturer is developing a product that will start in on...
Question 93: A project manager would like to bring vendors into a new pro...
Question 94: Due to a new government regulation, a project change is requ...
Question 95: A senior manager asks a project manager for an estimated bud...
Question 96: A change must be made to a project to comply with municipal ...
Question 97: A project manager travels abroad to meet the offshore team a...
Question 98: During a project assessment, a project manager determines th...
Question 99: A project manager provides status reports to a customer on a...
Question 100: A task on the critical path will not be completed on time. T...