CompTIA.PK0-004.v2020-11-25.q148

Exam Code:PK0-004
Exam Name:CompTIA Project+ Exam
Certification Provider:CompTIA
Free Question Number:148
Version:v2020-11-25
Rating:
# of views:246
# of Questions views:3678
Start Practice Test

Valid PK0-004 Dumps shared by Lead1Pass.com for Helping Passing PK0-004 Exam! Lead1Pass.com now offer the newest PK0-004 exam dumps, the Lead1Pass.com PK0-004 exam questions have been updated and answers have been corrected get the newest Lead1Pass.com PK0-004 dumps with Test Engine here:

Access Premium Version
(505 Q&As Dumps, 40%OFF Special Discount: freecram)

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
149 viewsCompTIA.PK0-004.v2021-01-25.q152
569 viewsCompTIA.PK0-004.v2019-11-07.q100
636 viewsCompTIA.PK0-004.v2018-11-12.q118
Exam Question List
Question 1: A PM has a complex project that requires coordination among ...
Question 2: New requirements were introduced during the execution phase ...
Question 3: Which of the following is an example of a project?...
Question 4: Which of the following features describe a projectized organ...
Question 5: A project manager procures additional resources from a local...
Question 6: Two critical members have approached the project manager sep...
Question 7: A project manager is attempting to establish the proper sequ...
Question 8: A new project manager is working in an environment where res...
Question 9: Which of the following charts is a mathematical diagram used...
Question 10: At a project kickoff meeting, several team members acted unp...
Question 11: A new contractor joining the project team is an example of:...
Question 12: An organization has determined that all projects must use a ...
Question 13: When developing a project schedule, which of the following t...
Question 14: A project team has completed a major deliverable earlier tha...
Question 15: An agreement document that is intended to prevent two or mor...
Question 16: There are four parallel paths on a network diagram. The summ...
Question 17: Which of the following are the BEST risk analysis tools to d...
Question 18: A project manager is creating the monthly report for top man...
Question 19: Which of the following charts is a graphical representation ...
Question 20: Tasks B and D start after Task A is completed. Task C starts...
Question 21: Which of the following is the primary purpose of an MOA or a...
Question 22: A project team member states that the tasks identified in th...
Question 23: The project manager has had a large number of change request...
Question 24: A contract review meeting has been scheduled with a non-perf...
Question 25: A vendor was removed from a company due to non-performance b...
Question 26: The PMO is confused by an entry in the risk register and wou...
Question 27: A project team is composed of numerous team members who are ...
Question 28: A project encountered a problem and reached a milestone. In ...
Question 29: The chairperson of the board is visiting from another countr...
Question 30: A senior manager asks a project manager for an estimated bud...
Question 31: A project team is overseeing the installation of a new repti...
Question 32: A project manager is scheduling activities and determines on...
Question 33: Which of the following techniques modifies the schedule base...
Question 34: A project team is identifying, rating the probability of, an...
Question 35: A customer has requested a new feature be included in the ne...
Question 36: Which of the following metrics demonstrates to a project man...
Question 37: Which of the following describes a project's budget overrun?...
Question 38: Company A and Company B have come together to form a new Com...
Question 39: A financial audit is being performed on a closed project. Wh...
Question 40: A project manager has an opportunity to add a highly skilled...
Question 41: The project team is moving from high-level risks to detailed...
Question 42: Which of the following is described as placing responsibilit...
Question 43: A program manager informs a project manager that a new, high...
Question 44: The project manager was asked to provide recommendations for...
Question 45: The project manager has noticed a vendor is not performing i...
Question 46: A vendor is unable to deliver an order by the specified date...
Question 47: An organization is divided into three separate entities base...
Question 48: An active project has a CPI of 0.92. Which of the following ...
Question 49: A project has activities on the critical path that must be c...
Question 50: Which of the following Agile ceremonies is used to determine...
Question 51: A project manager has contracted a third-party vendor to ach...
Question 52: When a risk event occurs, which of the following documents i...
Question 53: Which of the following defines the minimum level of engageme...
Question 54: Due to a lack of adherence to the risk response plan, there ...
Question 55: A new project sponsor has joined the project team, and the c...
Question 56: Which of the following should be included in an effective SO...
Question 57: A diagram or chart is required to illustrate data difference...
Question 58: A stakeholders asked for a change to the project. The projec...
Question 59: An industry leader may be joining the project team and can p...
Question 60: A project manager wants to introduce the practice of a WBS t...
Question 61: A company has hired a new project manager. The PMO has brief...
Question 62: Based on the table below: (Exhibit) Which of the following i...
Question 63: A manufacturer is developing a product that will start in on...
Question 64: During a risk review session, the project team identified th...
Question 65: A company decides to give a large section of its development...
Question 66: Three IT companies have agreed to summarize their efforts as...
Question 67: Which of the following activity sequencing techniques uses n...
Question 68: A project can be defined as:
Question 69: Which of the following documents will provide the MOST detai...
Question 70: A project manager is justifying a required change with the a...
Question 71: After SOW and contract approvals, the project manager plans ...
Question 72: The project schedule performance index is 1.1, and the cost ...
Question 73: A post implementation review is being performed as a part of...
Question 74: A department manager asks a project manager about the status...
Question 75: A team member was assigned a new task during a meeting. The ...
Question 76: An organization has multiple projects that are taking place ...
Question 77: A project team on a four-year project has a shortage of work...
Question 78: A team has been assembled and assigned a project to reduce r...
Question 79: Which of the following is a characteristic of a project?...
Question 80: A project team has just finished one phase of product develo...
Question 81: A project manager has been assigned a complex project and do...
Question 82: Which of the following activities are associated with the cl...
Question 83: One of the tasks on a project's critical path is progressing...
Question 84: A project manager is working on the project charter. Which o...
Question 85: A minor change to the baseline schedule is required. This ch...
Question 86: A project manager needs to track the actual and estimated st...
Question 87: Which of the following is a characteristics of a matrix orga...
Question 88: A project manager creates a Pareto chart based on the table ...
Question 89: The project sponsor has cut the resources required for proje...
Question 90: A project manager is reviewing documents to develop the proj...
Question 91: Which of the following defines a group of projects that work...
Question 92: A part that is needed to complete Task 3 has been backordere...
Question 93: A fire occurred in the production facility over the weekend,...
Question 94: A project has passed a phase-gate, and the new phase is read...
Question 95: A client has requested a project be completed ahead of sched...
Question 96: An organization wants assurance that the specialty tools nec...
Question 97: A project team started work on a project and was ahead of sc...
Question 98: A PM notes a feature that was delivered does not appear in t...
Question 99: A project manager is providing the lessons learned for a pro...
Question 100: An employee is assigned to a project and is developing a pro...
Question 101: The key stakeholders have reported the project pace as being...
Question 102: A project manager travels abroad to meet the offshore team a...
Question 103: Under an Agile methodology, standup meetings occur:...
Question 104: The business stakeholder has been engaged late and has just ...
Question 105: When a project team member completes a task in the WBS, whic...
Question 106: A project manager has been assigned a project with a budget ...
Question 107: Which of the following provides tools and standard documenta...
Question 108: Which of the following represents additional unauthorized re...
Question 109: The project team is not comfortable moving an expensive mate...
Question 110: Which of the following documents ensures two parties do not ...
Question 111: A project manager is assigned a project that is part of the ...
Question 112: A PM has notified the project team of an immediate project r...
Question 113: A project team member highlights to the project manager that...
Question 114: A project is about to begin the execution phase. The SOW and...
Question 115: The PM is preparing for the planning phase kickoff meeting. ...
Question 116: A risk with a high probability and medium consequence to a p...
Question 117: Which of the following is a team-building stage that involve...
Question 118: A software development project is struggling with a certain ...
Question 119: If a project sponsor wants to know the current status and pr...
Question 120: According to the communication management plan, the project ...
Question 121: Given the following sprint: (Exhibit) Which of the following...
Question 122: Which of the following are the roles involved in a Scrum pro...
Question 123: A project manager is not required to participate in performa...
Question 124: Rather than sending emails to communicate all project inform...
Question 125: In the review of a project status report, the slack is negat...
Question 126: Two team members completely disagree on how to complete a sp...
Question 127: Which of the following communication methods and target audi...
Question 128: Which of the following information does the project risk reg...
Question 129: A project team is not delivering their tasks in a timely man...
Question 130: Which of the following conflict resolution techniques relies...
Question 131: Communication on a project is flowing well. Team members are...
Question 132: A project manager has been asked to prepare and present a re...
Question 133: During the execution phase, the project manager discovered t...
Question 134: A project manager is archiving of project documents. Which o...
Question 135: Which of the following vendor documents specifically address...
Question 136: A sponsor requests that the project team shorten the complet...
Question 137: A new stakeholder has been added to a project with a BAG of ...
Question 138: Which of the following will identify the MOST potential proj...
Question 139: Which of the following describes how a project is related to...
Question 140: In which of the following situations is a project manager MO...
Question 141: Which of the following is a schedule that illustrates the du...
Question 142: Resources for a project report to a project manager and a fu...
Question 143: Which of the following make up a company's portfolio? (Choos...
Question 144: A company has dictated project scope changes but has stated ...
Question 145: A project has a BAC of $850,000. The project manager has ide...
Question 146: A project needs two more months of work to be completed, but...
Question 147: Two companies have merged. Which of the following may impact...
Question 148: Which of the following are MOST essential to developing an e...