PRINCE2.Prince2-Practitioner.v2019-01-22.q139

Exam Code:PRINCE2-Practitioner
Exam Name:PRINCE2 Practitioner Exam
Certification Provider:PRINCE2
Free Question Number:139
Version:v2019-01-22
Rating:
# of views:292
# of Questions views:7189
Start Practice Test

Valid PRINCE2-Practitioner Dumps shared by PrepAwayExam.com for Helping Passing PRINCE2-Practitioner Exam! PrepAwayExam.com now offer the newest PRINCE2-Practitioner exam dumps, the PrepAwayExam.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the newest PrepAwayExam.com PRINCE2-Practitioner dumps with Test Engine here:

Access Premium Version
(190 Q&As Dumps, 40%OFF Special Discount: freecram)

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
138 viewsPRINCE2.PRINCE2-Practitioner.v2019-07-06.q147
557 viewsPRINCE2.Prince2-Practitioner.v2018-07-25.q125
428 viewsPRINCE2.Prince2-practitioner.v2018-04-23.q191
Exam Question List
Question 1: Who is responsible for confirming stage and project progress...
Question 2: The Health and Safety Training Project is closing as planned...
Question 3: Which statement is TRUE with regard to technical stages?...
Question 4: This question provides a number of changes which may or may ...
Question 5: The project is at the start of stage 3, and there will be si...
Question 6: Which 2 statements apply to either the Reporting arrangement...
Question 7: An external consultant has signed a contract and agreed a wo...
Question 8: Which of the following reports does not contain any informat...
Question 9: Which of the following is the definition for an off-specific...
Question 10: While planning the initiation stage, the Project Manager rev...
Question 11: During which process would the stage tolerances be set?...
Question 12: Which 2 statements should be recorded under the Timescale he...
Question 13: What additional risk will this place on the project?...
Question 14: There are two time driven controls in PRINCE2, which are the...
Question 15: Which of the following principles describes this statement? ...
Question 16: ABC Company carried out a similar project two years ago, in ...
Question 17: A construction company that is one of ABC Company's key clie...
Question 18: According to PRINCE2, which statement about the Configuratio...
Question 19: Starting Up a project is triggered by which of the following...
Question 20: Which 2 alternative actions apply to the proposed supplier a...
Question 21: This question provides a number of changes which may or may ...
Question 22: While preparing the Quality Management Strategy, the Project...
Question 23: If the Project Board are too busy to authorize all change re...
Question 24: This question provides a number of changes which may or may ...
Question 25: Which 2 alternative actions apply to the proposed business a...
Question 26: Which of the following is NOT an objective of Initiating a P...
Question 27: This question provides a number of changes which may or may ...
Question 28: Which 2 alternative actions apply to the proposed Senior Sup...
Question 29: Who is responsible for ensuring that the value-for-money sol...
Question 30: Which of the following statements is true of the business in...
Question 31: None of the reviewers have proof-reading skills....
Question 32: Which 2 statements should be recorded under the Major risks ...
Question 33: Which 2 statements should be recorded under the Costs headin...
Question 34: In which Management product would the Project Board specify ...
Question 35: While preparing the Configuration Management Strategy, the P...
Question 36: There is no mention of any Stage Plans, yet there are two fu...
Question 37: Having created the Issue Report and analyzed the impact of r...
Question 38: Which of the following is not a factor to consider when dete...
Question 39: The project's change control approach states that PRINCE2's ...
Question 40: The external team manager for the 'e-learning course' has re...
Question 41: Which 2 statements apply to either the Techniques, processes...
Question 42: Which activity is responsible for updating the stage plan wi...
Question 43: The project is in stage 2. The project manager is reviewing ...
Question 44: Which of the following should NOT be included in the busines...
Question 45: There is no Project Brief. How can there be a common underst...
Question 46: In order for ABC Company to achieve the expected sales of th...
Question 47: Which of the following is NOT a trigger for the project mana...
Question 48: Which other management product is created when the Business ...
Question 49: This question provides a number of changes which may or may ...
Question 50: There is no project schedule in the Project Initiation Docum...
Question 51: Which product should show that the photos could be used for ...
Question 52: Although it is not specified in the current corporate brandi...
Question 53: ABC Company has decided to include the Health and Safety Tra...
Question 54: Which 2 statements apply to either the Extracts or reference...
Question 55: The Team Manager has received notification that the new hard...
Question 56: Which 2 statements should be recorded under the Expected ben...
Question 57: While capturing previous lessons, the Project Manager discov...
Question 58: Which of the following statements is TRUE with regard to exp...
Question 59: Which statement best explains the purpose of Tailor to suit ...
Question 60: Who is responsible for the initial creation of the Configura...
Question 61: Which of the following roles cannot be combined?...
Question 62: As the project approaches the end of stage 2, the Project Ma...
Question 63: According to PRINCE2, which statement about appointing the M...
Question 64: In which strategy would the change control process be record...
Question 65: The executive identified that there would be a benefit to th...
Question 66: The executive has set the following tolerances for stage 2: ...
Question 67: Towards the end of stage 2, the stage 3 plan is being prepar...
Question 68: Which of the following represents the four key characteristi...
Question 69: No Benefits Review Plan has been developed. Where should the...
Question 70: The project board has asked for highlight reports every six ...
Question 71: What will be the impact on the benefits?...
Question 72: Which product should show that the staff photo sessions were...
Question 73: Which 2 statements should be recorded under the Expected dis...
Question 74: The team member collating the list of customers has now fore...
Question 75: Which of the following statements is False regarding the Ris...
Question 76: Which statement is an appropriate entry for the outline Busi...
Question 77: If Project tolerances were threatened, who needs to be notif...
Question 78: MANAGING PRODUCT DELIVERY The team manager for the productio...
Question 79: ABC Company uses a standard development model to develop cou...
Question 80: Which of the following statements is FALSE regarding the Con...
Question 81: Who is responsible for ensuring that Communication Managemen...
Question 82: The Health and Safety Training Project is part of a programm...
Question 83: During stage 2, if the Project Manager decides to recommend ...
Question 84: MANAGING A STAGE BOUNDARY The ABC Company trainers have been...
Question 85: The service level agreement looks like any other MFH documen...
Question 86: Which of the following risk responses can be used for either...
Question 87: At the end of initiation there is +1 week 1-2 weeks time tol...
Question 88: Which of the following principles uses Product Descriptions ...
Question 89: During a work package the Team manager needs to keep the pro...
Question 90: Which of the following management products ARE updated as pa...
Question 91: During stage 3, the operational staff that handle course boo...
Question 92: The project is at the end of stage 4. The project manager ha...
Question 93: Which product should show that if anybody has any remaining ...
Question 94: Who is responsible for appointing the Project Manager?...
Question 95: What products will be impacted by this change?...
Question 96: Which product should register that the risk of a competitor ...
Question 97: Which is a correctly defined acceptance criterion for the ru...
Question 98: Which product should show that the project has been closed p...
Question 99: A quality review of the 'marketing materials' has started. T...
Question 100: While producing the Team Plan to deliver the agreed Work Pac...
Question 101: Which statement is an appropriate entry for the project appr...
Question 102: Which statement is an appropriate entry for the Lessons Log?...
Question 103: Which 2 alternative actions apply to the proposed Executive ...
Question 104: The development of the 'e-learning course' will be outsource...
Question 105: Who would be responsible for maintaining the Configuration I...
Question 106: All the products that are due in stage 3 have been completed...
Question 107: Which of the following activities could trigger the producti...
Question 108: Which product should show that without the calendar the comp...
Question 109: Which of the following activities is NOT an action of prepar...
Question 110: Which statement is an appropriate entry for the Initiation S...
Question 111: What is the purpose of a Product Status Account?...
Question 112: Which principle is supported by the activity Evaluate the Pr...
Question 113: Which of the following statements is FALSE regarding the Con...
Question 114: Which of the following is False? A Successful project manage...
Question 115: While preparing the Risk Management Strategy, the Project Ma...
Question 116: Which 2 alternative actions apply to the proposed Senior Use...
Question 117: Which is a correctly defined acceptance criterion for the tr...
Question 118: Which statement applies to the Introduction section?...
Question 119: Without a Risk Register how can project risks, the progress ...
Question 120: When examining a project issue, which three aspects should b...
Question 121: Which 2 statements should be recorded under the Expected ben...
Question 122: The Work Package has been in progress for four weeks and has...
Question 123: During Executing a Work package, specialist products are cre...
Question 124: Which 2 statements should be recorded under the Expected dis...
Question 125: During stage 1 the level of performance expected from the se...
Question 126: Which 2 statements should be recorded under the Timescale he...
Question 127: CLOSING A PROJECT Benefits relating to income and business r...
Question 128: Which 2 alternative actions apply to the proposed user assur...
Question 129: While deciding on how the work of the project should be appr...
Question 130: This question provides a number of changes which may or may ...
Question 131: This question provides a number of changes which may or may ...
Question 132: Whilst identifying the mailing costs for the calendars the P...
Question 133: At the end of stage 2, the specialist 'e-learning course' su...
Question 134: Which project controls should be established for the Outsour...
Question 135: The service level agreement contains a number of technical t...
Question 136: There are four steps in the Risk Management procedure, what ...
Question 137: During which of the following activities is the Project Prod...
Question 138: Which 2 statements apply to either the Development Interface...
Question 139: During stage 2, an early review of the photo design ideas fr...