Vendor.CAPM.v2019-07-03.q512

Exam Code:CAPM
Exam Name:
Certification Provider:Vendor
Free Question Number:512
Version:v2019-07-03
Rating:
# of views:124
# of Questions views:5825
Start Practice Test

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
179 viewsCWNP.CAPM.v2019-02-21.q471
Exam Question List
Question 1: The process of aggregating the estimated costs of individual...
Question 2: Which is the document that presents a hierarchical project o...
Question 3: Which statement about accepted deliverables is correct?...
Question 4: A special type of bar chart used in sensitivity analysis for...
Question 5: The degree of uncertainty an entity is willing to take on in...
Question 6: An input to the Plan Stakeholder Management process is:...
Question 7: Which activity may occur at project or phase closure?...
Question 8: The diagram below is an example of a: (Exhibit)...
Question 9: What is the most accurate rough order of magnitude (ROM)?...
Question 10: Project management processes ensure the:...
Question 11: A project manager is assigned to a strategic project. Senior...
Question 12: The risk shared between the buyer and seller is determined b...
Question 13: Which of the following consists of the detailed project scop...
Question 14: Which of the following methods is a project selection techni...
Question 15: Resource calendars are included in the:...
Question 16: Through whom do project managers accomplish work?...
Question 17: What is the name of a graphic display of project team member...
Question 18: Which of the following is a component of three-point estimat...
Question 19: Control charts, flowcharting, histograms, Pareto charts, and...
Question 20: Which technique helps to determine the risks that have the m...
Question 21: The scope of a project cannot be defined without some basic ...
Question 22: The project team is using their current information, abiliti...
Question 23: Plan-do-check-act is also known as:...
Question 24: Which process determines the correctness of deliverables?...
Question 25: Which cost estimate technique includes contingencies to acco...
Question 26: Which of the following are outputs of Develop Project Team?...
Question 27: Which type of analysis would be used for the Plan Quality pr...
Question 28: Which tool or technique of the Define Activities process all...
Question 29: After an internal deliverable review session with the team, ...
Question 30: Prioritizing risks for further analysis or action by assessi...
Question 31: What is the lowest level in the Work Breakdown Structure cal...
Question 32: A project manager builds consensus and overcomes obstacles b...
Question 33: Project deliverables that have been completed and checked fo...
Question 34: Which of the following is an input into the Develop Project ...
Question 35: Soft logic is also known as what type of dependency?...
Question 36: A project manager needs to deliver the project 2 weeks befor...
Question 37: When should quality planning be performed?...
Question 38: A reward can only be effective if it is:...
Question 39: Which tool or technique can a project manager use to select ...
Question 40: In project management, a temporary project can be:...
Question 41: The project manager is working in an agile/adaptive environm...
Question 42: Which process uses occurrence probability and impact on proj...
Question 43: Payback period, return on investment, internal rate of retur...
Question 44: A project manager requesting industry groups and consultants...
Question 45: What is a tool to improve team performance?...
Question 46: Change requests are processed for review and disposition acc...
Question 47: The degree, amount, or volume of risk that an organization o...
Question 48: During which process group is the quality policy determined?...
Question 49: What type of planning is used where the work to be accomplis...
Question 50: Which of the Project Time Management processes analyzes acti...
Question 51: Which of the following statements is true regarding project ...
Question 52: Which is an enterprise environmental factor?...
Question 53: Specification of both the deliverables and the processes is ...
Question 54: An electronics firm authorizes a new project to develop a fa...
Question 55: Which of the following processes are within the Initiating P...
Question 56: At which stage of team development do members begin to work ...
Question 57: What is the number of stakeholders, if the project has 28 po...
Question 58: A project can be defined as a:
Question 59: The project manager released a report. A few stakeholders ex...
Question 60: Which estimating technique uses the actual costs of previous...
Question 61: The initial development of a Project Scope Management plan u...
Question 62: A project management office manages a number of aspects incl...
Question 63: What is one of the objectives of Project Risk Management?...
Question 64: Projects are separated into phases or subprojects; these pha...
Question 65: Which Process Group typically consumes the bulk of a project...
Question 66: Those who enter into a contractual agreement to provide serv...
Question 67: Which of the following correctly describes when organization...
Question 68: Which item is an example of personnel assessment?...
Question 69: The creation of an internet site to engage stakeholders on a...
Question 70: Project Stakeholder Management focuses on:...
Question 71: Prototype development may be used as a tool for which of the...
Question 72: Regression analysis, failure mode and effect analysis (FMEA)...
Question 73: An element of the project scope statement is:...
Question 74: Which is a communication method used in the Report Performan...
Question 75: Which of the following documents are created as part of Proj...
Question 76: Taking out insurance in relation to risk management is calle...
Question 77: Which group creativity technique asks a selected group of ex...
Question 78: Which of the Perform Quality Assurance tools and techniques ...
Question 79: When painting a bedroom, preparing the walls can be done whi...
Question 80: The product scope description is used to:...
Question 81: Testing falls into which of the following categories of cost...
Question 82: When an activity cannot be estimated with a reasonable degre...
Question 83: Which tool or technique allows a large number of ideas to be...
Question 84: Which tool or technique is used to develop a project charter...
Question 85: Monte Carlo is which type of risk analysis technique?...
Question 86: What is the purpose of the project management process groups...
Question 87: A graphic display of project team members and their reportin...
Question 88: Which schedule development technique modifies the project sc...
Question 89: Which of the following is a tool or technique of the Define ...
Question 90: To which process is work performance information an input?...
Question 91: Which quality management and control tool is useful in visua...
Question 92: Reserve analysis is a tool and technique used in which proce...
Question 93: Using the three-point estimating technique, if the most like...
Question 94: Which tool or technique is used in Close Procurements?...
Question 95: Which tool within the Perform Quality Control process identi...
Question 96: The number of potential communication channels for a project...
Question 97: An issue log is an input to which Project Human Resource Man...
Question 98: The process of confirming human resource availability and ob...
Question 99: Which type of agreement is legal, contractual, and between t...
Question 100: Tools and techniques used for Plan Communications include th...
Question 101: The following chart contains information about the tasks in ...
Question 102: Which type of estimating can produce higher levels of accura...
Question 103: Status of deliverables, implementation status for change req...
Question 104: An imposed date for completion of the project by the custome...
Question 105: The iterative process of increasing the level of detail in a...
Question 106: What is the schedule performance index (SPI) if the planned ...
Question 107: An input to the Estimate Activity Resources process is:...
Question 108: Perform Quality Control is accomplished by:...
Question 109: A project manager is considering whether or not to procure a...
Question 110: Which of the following tools will be used to produce perform...
Question 111: In a project using agile methodology, who may perform the qu...
Question 112: Change request status updates are an output of which process...
Question 113: Which of the following is an input to the Perform Qualitativ...
Question 114: One of the fundamental tenets of modern quality management s...
Question 115: Which input to the Plan Risk Management process provides inf...
Question 116: An input to the Perform Integrated Change Control process is...
Question 117: A project manager at a publishing company decides to initiat...
Question 118: In a weak matrix, the project managers role is:...
Question 119: Which component of the human resource management plan descri...
Question 120: Requirements documentation, requirements management plan, an...
Question 121: Another name for an Ishikawa diagram is:...
Question 122: In Plan Risk Management, which of the management plans deter...
Question 123: During project selection, which factor is most important?...
Question 124: When a permitting agency takes longer than planned to issue ...
Question 125: A new project manager wishes to recommend creating a project...
Question 126: A project team member is estimating the cost of an activity ...
Question 127: Which Control Quality tool is also known as an arrow diagram...
Question 128: Which tool or technique is used in the Perform Integrated Ch...
Question 129: A full-time project manager with low to moderate authority a...
Question 130: A purchase order for a specified item to be delivered by a s...
Question 131: Which of the following are documented directions to perform ...
Question 132: If you established a contingency reserve including time, mon...
Question 133: A project manager needs to request outside support for a sta...
Question 134: In complex projects/ initiating processes should be complete...
Question 135: Which Plan Schedule Management tool or technique may involve...
Question 136: The process of estimating the type and quantity of material,...
Question 137: Which is the main benefit of managing and tailoring strategi...
Question 138: Risk responses reflect an organization's perceived balance b...
Question 139: Which of the following tasks focuses on decomposing work pac...
Question 140: An intentional activity to modify a nonconforming product or...
Question 141: Who determines which dependencies are mandatory during the S...
Question 142: Which is an input to the Verify Scope process?...
Question 143: When a backward pass is calculated from a schedule constrain...
Question 144: Who provides the inputs for the original estimates of activi...
Question 145: Which type of dependency is contractually required or inhere...
Question 146: Which standard examines an enterprise's project management p...
Question 147: Which is the correct formula for calculating expected activi...
Question 148: Definitions of probability and impact, revised stakeholder t...
Question 149: The lowest level normally depicted in a work breakdown struc...
Question 150: When does the project team determine which dependencies are ...
Question 151: In the Develop Project Team process, which of the following ...
Question 152: Cost variance (CV) is equal to earned value:...
Question 153: Which item is an output of Plan Quality Management and an in...
Question 154: The project manager is working with some functional managers...
Question 155: Retreating from an actual or potential conflict or postponin...
Question 156: Which is a tool used in monitoring and controlling project w...
Question 157: Which technique is utilized in the Control Schedule process?...
Question 158: What is the definition of Direct and Manage Project Executio...
Question 159: Which process determines the risks that might affect the pro...
Question 160: Which term describes an assessment of correctness?...
Question 161: Which tool or technique is used in the Estimate Costs proces...
Question 162: When large or complex projects are separated into distinct p...
Question 163: Which group of inputs will a project manager use during the ...
Question 164: Considering a highly dynamic project environment, which appr...
Question 165: The scope management plan and scope baseline are contained i...
Question 166: An input to Develop Project Charter is a/an:...
Question 167: An input required to develop a preliminary project scope sta...
Question 168: How should a stakeholder who is classified as high power and...
Question 169: Which type of risk diagram is useful for showing time orderi...
Question 170: An input to the Plan Cost Management process is:...
Question 171: Which of the following tools and techniques is used in the D...
Question 172: The process of prioritizing risks for further analysis or ac...
Question 173: Which of the following strategic considerations often result...
Question 174: A junior team member has been promoted to the position of pr...
Question 175: Sensitivity analysis is typically displayed as a/an:...
Question 176: Scope verification is PRIMARILY concerned with which of the ...
Question 177: The process improvement plan details the steps for analyzing...
Question 178: The following is a network diagram for a project. (Exhibit) ...
Question 179: Which tool or technique used in the Control Procurements pro...
Question 180: An input to the Manage Project Team process is:...
Question 181: The methodology that combines scope, schedule, and resource ...
Question 182: Which provides the basic framework for managing a project?...
Question 183: A project manager is working on project cost management. The...
Question 184: A project manager providing information to the right audienc...
Question 185: Which type of dependency used in the Sequence Activities pro...
Question 186: Which enterprise environmental factors are considered during...
Question 187: Which characteristic is unique to project work and does not ...
Question 188: When sequencing activities, what does the common acronym FF ...
Question 189: Which process is usually a rapid and cost-effective means of...
Question 190: The project manager is explaining to others the essential bu...
Question 191: The processes required to establish the scope of the project...
Question 192: Which of the following Process Groups covers all Project Man...
Question 193: Which of the following is a tool or technique used in the Ac...
Question 194: A risk that arises as a direct result of implementing a risk...
Question 195: Which of the following is an output of the Perform Integrate...
Question 196: The project has a current cost performance index of 0.80. As...
Question 197: Which of the following is developed from the project scope b...
Question 198: Which of the following is an output of Close Procurements?...
Question 199: Which of the following set of items belongs to the communica...
Question 200: Which of the following is a statistical concept that calcula...
Question 201: Which is one of the determining factors used to calculate CP...
Question 202: During which process of Project Cost Management does a proje...
Question 203: How is the Project Scope Management process different in agi...
Question 204: Which Develop Schedule tool and technique produces a theoret...
Question 205: When does Monitor and Control Risks occur?...
Question 206: An input to the Create WBS process is a:...
Question 207: Typical outcomes of a project include:...
Question 208: What should a project manager do to prepare a risk managemen...
Question 209: Which type of dependency is established based on knowledge o...
Question 210: Fast tracking is a schedule compression technique used to sh...
Question 211: Managing procurement relationships and monitoring contract p...
Question 212: A project manager should communicate to stakeholders about r...
Question 213: When a project is undertaken to reduce defects in a product ...
Question 214: Which input to Collect Requirements is used to identify stak...
Question 215: An output of the Create WBS process is:...
Question 216: An output of the Validate Scope process is:...
Question 217: The project manager and the project team are having a meetin...
Question 218: What causes replanning of the project scope?...
Question 219: At the end of the project, what will be the value of SV?...
Question 220: Which of the following is an example of a risk symptom?...
Question 221: The project manager notes that stakeholders are aware of the...
Question 222: An output of the Plan Quality Management process is:...
Question 223: Under which circumstances should multiple projects be groupe...
Question 224: Lessons learned are created and project resources are releas...
Question 225: Which are the competing constraints that a project manager s...
Question 226: Activity cost estimates are quantitative assessments of the ...
Question 227: Which of the following is a means of reaching a group decisi...
Question 228: A project manager is updating their CV or resume and realize...
Question 229: Which Project Time Management process includes bottom-up est...
Question 230: The cost of nonconformance in a project includes:...
Question 231: A project manager is working in an environment where require...
Question 232: Inputs to the Plan Risk Management process include the:...
Question 233: An element of the modern quality management approach used to...
Question 234: Market conditions and published commercial information are e...
Question 235: Which type of project management office (PMO) supplies templ...
Question 236: Which type of management focuses on ensuring that projects a...
Question 237: A disadvantage associated with virtual teams is that they:...
Question 238: An important project stakeholder has low risk tolerance. Whi...
Question 239: The contract in which the seller is reimbursed for all allow...
Question 240: Which characteristic do projects and operational work share ...
Question 241: In which project cost management process is work performance...
Question 242: During which process does the project team receive bids and ...
Question 243: Which group is formally chartered and responsible for review...
Question 244: Which conflict resolution technique is based on bringing som...
Question 245: Which of the following is a project constraint?...
Question 246: What type of project structure is a hierarchically organized...
Question 247: The output that defines an approach to increase the support ...
Question 248: Using parametric estimating, if an assigned resource is capa...
Question 249: Information collected on the status of project activities be...
Question 250: Outputs of the Control Communications process include:...
Question 251: Analogous cost estimating relies on which of the following t...
Question 252: Which is an example of an internal enterprise environmental ...
Question 253: The component of the risk management plan that documents how...
Question 254: Which category of contracts are sellers legally obligated to...
Question 255: Who MUST know when a risk event occurs so that a response ca...
Question 256: Which statement describes the Monitor Communications process...
Question 257: Changes to formally controlled documentation, plans, etc. to...
Question 258: Which written document helps monitor who is responsible for ...
Question 259: Which document describes the procurement item in sufficient ...
Question 260: What is the name of the statistical method that helps identi...
Question 261: Which Process Group contains those processes performed to de...
Question 262: The basis of identification for current or potential problem...
Question 263: When can pre-assignment of project team members occur?...
Question 264: Which stakeholder communicates with higher levels of managem...
Question 265: What should the project manager use to evaluate the politics...
Question 266: Which type of contract is a hybrid of both a cost-reimbursab...
Question 267: How many Project Management Process Groups are there?...
Question 268: The completion of the project scope is measured against the:...
Question 269: The project manager needs to manage a critical issue immedia...
Question 270: Which of the following is a group decision-making technique?...
Question 271: An input required in Define Scope is an organizational:...
Question 272: Outputs from constituent processes might be used as:...
Question 273: How is the schedule variance calculated using the earned val...
Question 274: A tool and technique used during the Collect Requirements pr...
Question 275: Which tools and techniques will a project manager use to dev...
Question 276: Which of the following Project Communication Management proc...
Question 277: Managing ongoing production of goods and services to ensure ...
Question 278: Which Control Scope input is compared to actual results to d...
Question 279: The Define Scope process is in which of the following Proces...
Question 280: A complete set of concepts, terms, and activities that make ...
Question 281: Which document describes the necessary information to determ...
Question 282: Which is an input to the Scope Verification Process?...
Question 283: Skills necessary for project management such as motivating t...
Question 284: Due to today's competitive global market, organizations requ...
Question 285: The cost baseline and project funding requirements are outpu...
Question 286: Which tools or techniques will a project manager use for Dev...
Question 287: External organizations that have a special relationship with...
Question 288: In which type of contract are the performance targets establ...
Question 289: Which factors should be considered for cross-cultural commun...
Question 290: A work package has been scheduled to cost $1,000 to complete...
Question 291: The organization's perceived balance between risk taking and...
Question 292: The process of monitoring the status of the project to updat...
Question 293: The Identify Stakeholders process is found in which Process ...
Question 294: Which of the following is an example of push communication?...
Question 295: Which of the following are outputs from the process of creat...
Question 296: Which process involves aggregating the estimated costs of th...
Question 297: The group technique that enhances brainstorming with a votin...
Question 298: Which is the best way for a project manager to ensure effici...
Question 299: Which of the following is an example of schedule compression...
Question 300: One of the key benefits of the Plan Human Resource Managemen...
Question 301: Which Process Group includes the Manage Stakeholder Engageme...
Question 302: Which of the following is an input to Direct and Manage Proj...
Question 303: The planned work contained in the lowest level of work break...
Question 304: A project stakeholder is requesting changes to the project p...
Question 305: Which input to the Manage Stakeholder Engagement process pro...
Question 306: Which of the following set of elements is part of an effecti...
Question 307: The project manager is dividing the project scope into small...
Question 308: Which tools or techniques are used during the Close Project ...
Question 309: Identifying major deliverables, deciding if adequate cost es...
Question 310: The following is a network diagram for a project. (Exhibit) ...
Question 311: Which are the most important competencies required for a pro...
Question 312: Which of the following methods of performance review examine...
Question 313: A project team member agrees to change a project deliverable...
Question 314: The integrative nature of project management requires which ...
Question 315: Which of the following includes how requirements activities ...
Question 316: The links between the processes in the Process Groups are of...
Question 317: When cost variance is negative and schedule variance is posi...
Question 318: Which is the Define Scope technique used to generate differe...
Question 319: The process of identifying the stakeholders' information nee...
Question 320: Which of the following is an input to Control Scope?...
Question 321: Which kind of communication should the project manager use w...
Question 322: When the business objectives of an organization change, proj...
Question 323: What is the estimate at completion (EAC) if the budget at co...
Question 324: Perform Integrated Change Control is the process of:...
Question 325: Which of the following is a set of interrelated actions and ...
Question 326: Which project risk listed in the table below is most likely ...
Question 327: Expected monetary value (EMV) is computed by which equation?...
Question 328: A project lifecycle is defined as:...
Question 329: Which of the following is an input to the Plan Risk Response...
Question 330: Which document includes the project scope, major deliverable...
Question 331: Project managers who lead by example and follow through on t...
Question 332: Which of the following is an output of the Plan Quality proc...
Question 333: Which of the following is an output of the Distribute Inform...
Question 334: The project manager is distributing project communications, ...
Question 335: An output of the Direct and Manage Project Work process is:...
Question 336: Tools and techniques used in Direct and Manage Project Work ...
Question 337: Which tool or technique is used in the Develop Project Manag...
Question 338: Which of the following are examples of interactive communica...
Question 339: Documented identification of a flaw in a project component t...
Question 340: Which index is the calculated projection of cost performance...
Question 341: Conditions that are not under the control of the project tea...
Question 342: A tool and technique used during the Perform Qualitative Ris...
Question 343: As part of a mid-project evaluation, the project sponsor has...
Question 344: Which key interpersonal skill of a project manager is define...
Question 345: Which of the following are an enterprise environmental facto...
Question 346: Portfolio Management is management of:...
Question 347: The process of formalizing acceptance of the completed proje...
Question 348: The project manager at an organization has just realized tha...
Question 349: Which Activity Duration Estimating technique incorporates ad...
Question 350: Exhibit A is an example of which of the following types of S...
Question 351: If a project manager effectively manages project knowledge, ...
Question 352: What are the project management processes associated with pr...
Question 353: A procurement management plan is a subsidiary of which other...
Question 354: A project using the agile/adaptive approach has reached the ...
Question 355: Which standard has interrelationships to other project manag...
Question 356: Which type of probability distribution is used to represent ...
Question 357: Projects are authorized by which of the following individual...
Question 358: Which type of contract is most commonly used by buying organ...
Question 359: Assigned risk ratings are based upon:...
Question 360: What is an objective of the Develop Project Team process?...
Question 361: The following is a network diagram for a project. (Exhibit) ...
Question 362: Which tool or technique is used in validating the scope of a...
Question 363: Which of the following are inputs for the Plan Quality Manag...
Question 364: Which of the following are the components of the scope basel...
Question 365: While implementing an approved change, a critical defect was...
Question 366: Which of the following is a schedule network analysis techni...
Question 367: Design of experiments (DOE) should be used during which of t...
Question 368: The process of establishing the policies, procedures, and do...
Question 369: Quality metrics are an output of which process?...
Question 370: To which knowledge area does the Collect Requirements proces...
Question 371: While processes in the Planning Process Group seek to collec...
Question 372: Inputs to the Plan Schedule Management process include:...
Question 373: What is the difference between the critical path and the cri...
Question 374: The process of defining how the project scope will be valida...
Question 375: With regard to a project manager's sphere of influence in a ...
Question 376: Which type of manager is assigned by the performing organiza...
Question 377: An input of the Create WBS process is:...
Question 378: Which item is a cost of conformance?...
Question 379: What type of reward can hurt team cohesiveness?...
Question 380: Which is a list of organizational systems that may have an i...
Question 381: Which is a difference between leadership and management?...
Question 382: A contractor has provided hands-on training to a team member...
Question 383: Requirements documentation will typically contain at least:...
Question 384: The review of a sellers progress toward achieving the goals ...
Question 385: Which process is responsible for monitoring the status of th...
Question 386: When managing costs in an agile environment, what should a p...
Question 387: The Monitoring and Controlling Process Group includes proces...
Question 388: The cost benefit analysis tool is used for creating:...
Question 389: Which tool or technique is used in the Plan Scope Management...
Question 390: The project manager has the following information about the ...
Question 391: Which item is a formal proposal to modify any document, deli...
Question 392: Which of the following helps to ensure that each requirement...
Question 393: Which process involves determining, documenting, and managin...
Question 394: What scope definition technique is used to generate differen...
Question 395: After Define Activities and Sequence Activities, the next pr...
Question 396: The purpose of inspection in Perform Quality Control is to k...
Question 397: Administer Procurements is part of which Process Group?...
Question 398: Which set of activities should a project manager use as part...
Question 399: Which type of chart is a graphic representation of a process...
Question 400: Which type of managers do composite organizations involve?...
Question 401: Plan Communications Management develops an approach and plan...
Question 402: Overlooking negative stakeholders can result in a/an:...
Question 403: If the most likely duration of an activity is five weeks, th...
Question 404: Which of the following tools and techniques is used to estim...
Question 405: An output of the Manage Project Team process is:...
Question 406: Change requests, project management plan updates, project do...
Question 407: Which of the following statements best describes the influen...
Question 408: Which changes occur in risk and uncertainty as well as the c...
Question 409: Which of the following change requests can bring expected fu...
Question 410: Organizational process assets can be divided into which of t...
Question 411: In the Estimate Activity Durations process, productivity met...
Question 412: Inputs to the Define Activities process include:...
Question 413: Which type of elaboration allows a project management team t...
Question 414: Stakeholders can be identified in later stages of the projec...
Question 415: Which of the following is a tool and technique used in the D...
Question 416: Projects can intersect with an organization's operations at ...
Question 417: Which Knowledge Area is concerned with the processes require...
Question 418: The Project Human Resource Management process that involves ...
Question 419: Which process involves developing an approximation of the mo...
Question 420: Which type of contract gives both the seller and the buyer f...
Question 421: What is the schedule performance index (SPI) using the follo...
Question 422: In a preliminary meeting for a project, team members decide ...
Question 423: Which process documents the business needs of a project and ...
Question 424: Which items are an output of the Perform Integrated Change C...
Question 425: Which activity involves ensuring that the composition of a p...
Question 426: The three processes of Project Cost Management are:...
Question 427: A given schedule activity is most likely to last four weeks....
Question 428: Which tasks should a project manager accomplish in order to ...
Question 429: Sharing good practices introduced or implemented in similar ...
Question 430: What cost control technique is used to compare actual projec...
Question 431: The activity of tailoring is necessary because:...
Question 432: Which can be used to determine whether a process is stable o...
Question 433: Within a matrix organization, dual reporting of team members...
Question 434: Which document defines how a project is executed, monitored ...
Question 435: Updates to organizational process assets such as procurement...
Question 436: The project governance approach should be described in the:...
Question 437: A stakeholder is reading project documents given by the proj...
Question 438: Which of the following is an output from Control Scope?...
Question 439: Which input provides suppliers with a clear set of goals, re...
Question 440: Which set of competencies should a project manager have?...
Question 441: Which input to the Identify Stakeholders process provides in...
Question 442: A change log for communications can be used to communicate t...
Question 443: An output of the Manage Stakeholder Engagement process is:...
Question 444: Which document in the project management plan can be updated...
Question 445: Which of the following risk response strategies involves all...
Question 446: The correct equation for schedule variance (SV) is earned va...
Question 447: What entity is assigned various responsibilities related to ...
Question 448: In which domain of project management would a Pareto chart p...
Question 449: The individual or group that provides resources and support ...
Question 450: Which project documents can determine the budget?...
Question 451: What happens to a stakeholder's project influence over time?...
Question 452: Which of the following is an information gathering technique...
Question 453: Which statement correctly describes the value of a business ...
Question 454: Which components of the project can be updated as a result o...
Question 455: What does a CPI value greater than 1.0 indicate?...
Question 456: Which of the following is a conflict resolution technique th...
Question 457: Which is the order of steps in the Procurement Management pr...
Question 458: Which of the following is an output of the Conduct Procureme...
Question 459: A benefit of using virtual teams in the Acquire Project Team...
Question 460: A project team attempts to produce a deliverable and finds t...
Question 461: Which are examples of processes that may be used once or at ...
Question 462: The Process Group in which the internal and external stakeho...
Question 463: The ability to influence cost is greatest during which stage...
Question 464: Conflict should be best addressed in which manner?...
Question 465: While preparing the project management plan on a weekly basi...
Question 466: What risk technique is used to quantify the probability and ...
Question 467: Projects can be divided into phases to provide better manage...
Question 468: The business needs, assumptions, and constraints and the und...
Question 469: The CPI is .92, and the EV is US$172,500.What is the actual ...
Question 470: Which of the following is a tool and technique for Estimate ...
Question 471: Which of the following is an enterprise environmental factor...
Question 472: An output of the Perform Integrated Change Control process i...
Question 473: Which of the following is a complete set of indexed contract...
Question 474: What process determines which risks might affect the project...
Question 475: Which process identifies whether the needs of a project can ...
Question 476: Which type of analysis is used to determine the cause and de...
Question 477: Cost of quality (COQ) refers to total cost of/to:...
Question 478: Project or phase closure guidelines or requirements, histori...
Question 479: The following is a network diagram for a project. (Exhibit) ...
Question 480: Which process is included in the Project Integration Managem...
Question 481: Which technique is commonly used for the Perform Quantitativ...
Question 482: The following is a network diagram for a project. (Exhibit) ...
Question 483: Under which type of contract does the seller receive reimbur...
Question 484: The project scope statement and resource calendars are input...
Question 485: In an adaptive project environment, which action helps the p...
Question 486: Which process involves the creation of a document that provi...
Question 487: A project charter is an output of which Process Group?...
Question 488: The project management processes are usually presented as di...
Question 489: A project manager needs to demonstrate that the project meet...
Question 490: Which of the following strategies is used to deal with risks...
Question 491: Which items are components of a project management plan?...
Question 492: A project manager can choose from several techniques to reso...
Question 493: Which type of analysis is used as a general management techn...
Question 494: A project manager is preparing to meet with three crucial pr...
Question 495: Which of the following is an estimating technique that uses ...
Question 496: Which tool or technique is an examination of industry and sp...
Question 497: Which of the following response strategies are appropriate f...
Question 498: The procurement process that documents agreements and relate...
Question 499: Which of the following is an output of the Monitor and Contr...
Question 500: "Tailoring" is defined as the:
Question 501: Which of the following correctly lists the configuration man...
Question 502: A project has an EV of 100 workdays, an AC of 120 workdays, ...
Question 503: A project is in the planning phase. The project manager is c...
Question 504: A strengths, weaknesses, opportunities, and threats (SWOT) a...
Question 505: According to PMBOK, the definition of Plan Risk Management i...
Question 506: Plan Schedule Management is a process in which Knowledge Are...
Question 507: Which type of project life cycle uses an iteration plan?...
Question 508: Which process involves identifying and documenting the logic...
Question 509: Which input to the Manage Stakeholder Engagement process is ...
Question 510: Which grid shows which resources are tied to work packages?...
Question 511: Decomposition, rolling wave planning, and templates are all ...
Question 512: Which technique should a project manager use in a situation ...