Microsoft Project 2010, Managing Projects - 070-178 FREE EXAM DUMPS QUESTIONS & ANSWERS

You want to print the Gantt Chart view of your project. You need to hide the Gantt chart legend. What should you do?
Correct Answer: B Vote an answer
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
Correct Answer: C Vote an answer
You manage several projects saved on a shared drive. You want to create a critical path relationship between several schedules managed by other project managers. You need to link the project schedules at the task level. You also need to ensure that each project manager can continue to manage their own project. What should you do?
Correct Answer: B Vote an answer
You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?
Correct Answer: D Vote an answer
In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
-Tasks that are not started.
-Tasks in progress.
-Tasks that have finished.
-Total remaining effort for each group of tasks.
What should you do on the View tab?
Correct Answer: C Vote an answer
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
Correct Answer: A Vote an answer
You use Project Professional 2010 to manage a construction project. Different members of the project team frequently modify a blueprint file. The file is saved in a Microsoft Office SharePoint document library. You need to access the file from within the project schedule. What should you do?
Correct Answer: D Vote an answer