Microsoft Project 2010, Managing Projects - 70-178 FREE EXAM DUMPS QUESTIONS & ANSWERS

Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
Correct Answer: D Vote an answer
You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?
Correct Answer: E Vote an answer
You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
Correct Answer: A Vote an answer
You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.)

You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,E Vote an answer
Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?
Correct Answer: C Vote an answer
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
Correct Answer: D Vote an answer
You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?
Correct Answer: D Vote an answer