PMI Risk Management Professional - PMI-RMP FREE EXAM DUMPS QUESTIONS & ANSWERS

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.
Given the project ' s complexity, what should the risk manager do?
Correct Answer: C Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations.
The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Correct Answer: D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.
How should the risk manager address this concern?
Correct Answer: A Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.
Correct Answer: D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
Correct Answer: C Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?
Correct Answer: A Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.
What should the risk manager advise the project team?
Correct Answer: C Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the project manager do next to determine risk impact of assumptions and constraints?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?
Correct Answer: D Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a
50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
Correct Answer: B Vote an answer
Explanation: Only visible for FreeCram members. You can sign-up / login (it's free).
0
0
0
10