Get 2024 Most Reliable Oracle 1z0-1075-24 Training Materials [Q22-Q40]

Share

Get 2024 Most Reliable Oracle 1z0-1075-24 Training Materials

The Realest Study Materials 1z0-1075-24 Dumps

NEW QUESTION # 22
You have been asked to set up cost estimates for 10 different purchased items. Which two tasks can you perform to achieve this?

  • A. Call a web service.
  • B. Enter cost estimates directly into the UI.
  • C. Import a spreadsheet.
  • D. Use the Mass Edit functionality.
  • E. Run the "Update Item Cost Estimate" ESS process.

Answer: B,C

Explanation:
To set up cost estimates for multiple purchased items in Oracle Manufacturing Cloud, the following tasks can be performed:
Import a spreadsheet (A): You can import cost estimates for multiple items at once using a preformatted spreadsheet, which allows for efficient data entry.
Enter cost estimates directly into the UI (E): Cost estimates can also be manually entered directly through the user interface for individual items, providing flexibility when fewer items need to be updated.
Incorrect options:
Calling a web service (B) is not the correct method for setting up cost estimates.
Mass Edit functionality (C) and Update Item Cost Estimate process (D) do not directly apply to entering new cost estimates for purchased items.


NEW QUESTION # 23
In which three ways does Supply Chain Orchestration enrich supply requests with project details to support outside processing for a project-specific work order?

  • A. Expenditure Item Date is set to the receipt date and Expenditure Organization is set to the manufacturing plant.
  • B. Supply Chain Orchestration initiates the creation of a requisition with the project details.
  • C. Supply Chain Orchestration initiates the creation of a purchase order without the work order.
  • D. Expenditure Type is sat to the expenditure type associated to the outside processing Item.
  • E. Expenditure Item Date Is set to the requested need-by date and Expenditure Organization is set to the manufacturing plant.

Answer: B,D,E

Explanation:
Supply Chain Orchestration (SCO) plays a vital role in managing project-specific work orders, particularly for outside processing. Here's how it enriches supply requests with project details:
Statement B: Expenditure Item Date is set to the requested need-by date and Expenditure Organization is set to the manufacturing plant - In project-specific work orders, Supply Chain Orchestration assigns the need-by date as the Expenditure Item Date. The Expenditure Organization is typically set to the manufacturing plant handling the work order.
Reference:
Statement D: Supply Chain Orchestration initiates the creation of a requisition with the project details - SCO automatically creates a requisition with all relevant project details, such as project number, task, and expenditure information. This ensures that the procurement process is aligned with the project's financial and material requirements.
Statement E: Expenditure Type is set to the expenditure type associated with the outside processing item - In Oracle Cloud, expenditure types must align with the specific processing items. SCO ensures that the correct expenditure type is applied to the work order and subsequent requisitions.
Incorrect Statements:
Statement A: SCO does not initiate the creation of a purchase order without the work order. A work order is essential for processing the outside work, and its absence would disrupt the orchestration process.
Statement C: The Expenditure Item Date is not set to the receipt date but rather to the requested need-by date for proper alignment with project scheduling.


NEW QUESTION # 24
Your client's company is in a regulated industries and must keep detailed records of their product manufacturing processes in accordance with the United States Food and Drug Administration (FDA) regulation on electronic records and signatures called 21 Code of Federal Regulations (CFR) Part 11.
You are implementing Oracle E-Signatures and E-Records for securely capturing, storing, retrieving, and printing electronic records and signatures in manufacturing. They enable Deferred Electronic Records and Electronic Signatures for Manufacturing Work Order Release in Oracle Manufacturing Cloud.
Which statement is NOT true about using Deferred Electronic Records and Electronic Signatures for Manufacturing Work Order Release?

  • A. Using a deferred approval process with notifications, the work order is held in "Released" status until the approvals are obtained.
  • B. These capabilities are supported for discrete and process work orders.
  • C. If the e-record is rejected, you can optionally resubmit the rejected electronic records.
  • D. It generates e-records on initial work order release through UI and sends notifications to approvers.

Answer: A

Explanation:
When implementing Oracle E-Signatures and E-Records for compliance with 21 CFR Part 11 in regulated industries like the pharmaceutical or food industries, certain processes govern how electronic records and signatures are managed for manufacturing work orders. The statement that is not true is:
Statement B is incorrect because when using deferred electronic records and signatures, the work order is not held in a "Released" status until approvals are obtained. Instead, the work order is placed in a "Pending Approval" state until signatures are collected and approval is granted. Only after approval does the work order move to a "Released" status.
Correct statements:
Statement A: E-records are generated at the time of work order release, and notifications are sent to approvers for review.
Statement C: Rejected e-records can be resubmitted for approval if necessary.
Statement D: These capabilities are supported for both discrete and process manufacturing work orders.


NEW QUESTION # 25
Which option represents all the production exception types that can be reported by a Production Operator in Oracle Manufacturing Cloud?

  • A. Work Area, Work Center, Resources, and Components
  • B. Work Center and Resources
  • C. Work Area. Work Center. Resources, Components, and Miscellaneous
  • D. Resources and Components
  • E. Work Area, Work Center, and Resources

Answer: A

Explanation:
In Oracle Manufacturing Cloud, production operators can report several types of production exceptions that affect the flow of the production process. The complete list of production exception types that can be reported includes:
Work Area: Issues related to the broader production environment.
Work Center: Problems or exceptions that arise at specific work centers.
Resources: Issues with labor, machines, or tools that are part of the production process.
Components: Exceptions related to materials or components used in manufacturing.
Incorrect options:
Options A, B, C, D are incomplete and miss one or more of the exception types available in Oracle Manufacturing Cloud.


NEW QUESTION # 26
Your client informs you that after running the "Process Item Structure Changes to Work Definitions" scheduled process, they received a workflow notification.
Which statement is NOT a workflow notification that you might get if automation is not performed?

  • A. The original component has been assigned to more than one work definition operation.
  • B. The manufacturing plant Is enabled for ERES, the work definition changes are not expected to go through an approval process.
  • C. The replacement component has been assigned as an ad hoc Item to the same operation as the original component.
  • D. The original component is not assigned to any work definition operation.

Answer: B

Explanation:
After running the "Process Item Structure Changes to Work Definitions" scheduled process, a series of workflow notifications may be triggered if the automation is not performed properly. The following notifications can be expected in scenarios where manual intervention is needed:
Statement B is incorrect because, in Oracle Manufacturing Cloud, if the manufacturing plant is enabled for ERES (Engineering Release Execution System), it generally implies that any changes in work definitions would still require an approval process for validation and control. The fact that ERES is enabled would not automatically bypass the approval process.
Correct Notifications:
Statement A: You may receive a notification that a replacement component has been assigned as an ad hoc item to the same operation where the original component was assigned.
Statement C: A notification may alert you that the original component is not assigned to any work definition operation, signaling a potential issue that requires manual intervention.
Statement D: It is also possible to receive a notification indicating that the original component has been assigned to more than one work definition operation, which may require review or adjustment.


NEW QUESTION # 27
Which three types of item quantities are displayed on the Work Order History tab?

  • A. Total
  • B. In Process
  • C. Remaining
  • D. Completed
  • E. Scrapped

Answer: B,D,E

Explanation:
The Work Order History tab in Oracle Manufacturing Cloud provides a summary of different item quantities related to the lifecycle of a work order. The following quantities are displayed:
In Process: This shows the quantity of items currently being processed in the production cycle.
Scrapped: This quantity reflects the number of items that have been discarded due to defects or other issues during the production process.
Completed: This quantity shows the number of items that have successfully been completed in the work order.
Incorrect options:
Remaining: The system does not specifically display a "Remaining" quantity on the Work Order History tab.
Total: The total quantity is not shown as a standalone metric in the Work Order History tab but is implied by other metrics.


NEW QUESTION # 28
In a Manufacturing Cloud implementation, users are finding it difficult to track information about work orders executed across various work centers.
Which three information types in the Work Order Traveler can help users in this situation?

  • A. Item on-hand quantity
  • B. Reservation against sales orders
  • C. Product serial Information
  • D. Work definition details
  • E. Hard pegging of items

Answer: B,C,D

Explanation:
The Work Order Traveler in Oracle Manufacturing Cloud provides detailed information about work orders to help users track and manage work orders across various work centers. The following types of information are especially useful:
Work definition details (D): This provides detailed information about the operations and resources required to complete the work order, helping users understand the manufacturing process and requirements.
Product serial information (E): Tracking serial numbers for products is critical, especially in industries where traceability and product lifecycle management are important.
Reservation against sales orders (A): This information links work orders to specific sales orders, providing clarity on how the work order aligns with customer demand.
Incorrect options:
Hard pegging of items (B) and Item on-hand quantity (C) are not typically tracked through the Work Order Traveler report, as this report focuses more on the work order's execution rather than inventory management.


NEW QUESTION # 29
Your customer has multiple distribution centers and a few manufacturing plants. The plants manufacture different items with some overlap between them. The distribution centers stock parts from all plants.
A Corporate Engineering team is responsible for centrally defining items and catalogs. This team defines the items and sets the attributes for most parameters. The respective distribution centers and manufacturing plants must be allowed to change some attributes locally.
What is the best way to achieve this?

  • A. Set up plants and the Corporate Engineering organization as Inventory organizations, and distribution centers as item organizations.
  • B. Set up plants as inventory organizations, and distribution centers and the corporate Engineering organization as item organizations.
  • C. Set up plants and distribution centers as inventory organizations, and the Corporate Engineering organization as an Item organization.
  • D. Set up plants and the Corporate Engineering organization as item organizations, and distribution centers as inventory organizations.
  • E. Set up plants, distribution centers, and the Corporate Engineering organization as inventory organizations.

Answer: C

Explanation:
In Oracle Cloud, managing items and their attributes across multiple organizations requires careful structuring of inventory and item organizations. The best way to configure this setup given the customer's requirements is as follows:
Plants and Distribution Centers as Inventory Organizations: Inventory organizations are required to manage on-hand quantities, perform transactions, and handle the physical movement of materials. Plants need to be inventory organizations to manage production, and distribution centers need to be inventory organizations to manage stocking and distribution.
Corporate Engineering Organization as an Item Organization: An item organization is responsible for centrally defining item attributes. By setting the Corporate Engineering team as an item organization, you ensure that item definitions are controlled centrally. The team can define standard attributes while allowing inventory organizations (plants and distribution centers) to modify certain attributes at their level based on local needs.
This structure allows for centralized item management with localized flexibility for plants and distribution centers.
Reference:
Incorrect Options:
A: Defining all entities as inventory organizations would not allow centralized control of item attributes.
C, D, E: These setups would either limit the ability to control item attributes centrally or misassign organizations that need to handle physical inventory as item-only organizations.


NEW QUESTION # 30
During a Manufacturing Cloud implementation, a Production Supervisor wants to close the work orders for the previous month and make sure that they include the correct cost.
What must they do to achieve this?

  • A. Include all costs and variances in last month's work orders and close them; however, the work orders where updates are expected must not be closed.
  • B. Exclude cost variances while closing last month's work orders because those can be applied directly In Subledger Accounting.
  • C. Make sure that all costs are Included while closing last month's work orders; however, variances can be Included after closing the work orders.
  • D. Update work order costs at any time; they can be updated regardless of the status of the work order

Answer: A

Explanation:
To ensure that work orders for the previous month are closed with the correct costs, the Production Supervisor must:
Include all costs and variances in the work orders before closing them. This ensures that the work orders reflect the true cost of production, including any deviations from the expected costs. However, if there are work orders that are still in progress or expected to receive updates (such as material or labor transactions), those work orders should not be closed until all costs are finalized.
Incorrect options:
A: Excluding cost variances would result in inaccurate costing.
B: All costs, including variances, must be included before closing.
D: Costs cannot be updated after the work order is closed, so all updates must occur before closing the work order.


NEW QUESTION # 31
Which statement is NOT true about user-defined work order statuses?

  • A. The system automatically updates user-defined work order statuses.
  • B. They are displayed on work order reports.
  • C. All the new statuses are searchable so you can filter your job and manage the work order life cycle more easily.
  • D. It is not recommended to update the name of the system status.

Answer: A

Explanation:
User-defined work order statuses provide flexibility in managing the lifecycle of work orders in Oracle Manufacturing Cloud. However, the following is not true:
The system does not automatically update user-defined work order statuses. These statuses are manually updated by users to reflect the work order's progress through custom-defined states.
Correct statements:
Displayed on work order reports: User-defined statuses are visible in work order reports, allowing users to track the status of different orders.
Name changes to system status: It is not recommended to alter system-defined status names as it could disrupt core system processes and workflows.
Searchability of new statuses: User-defined statuses are searchable, making it easier to manage and track work orders.


NEW QUESTION # 32
You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Which setup task must you perform to achieve this?

  • A. Ensure that the Charge Type of the resource is Automatic.
  • B. Select the Count Point check box while defining the standard operation.
  • C. Deselect the Count Point check box while defining the standard operation.
  • D. Select the Automatically Transact check box while defining the standard operation.

Answer: B

Explanation:
In Oracle Manufacturing Cloud, when defining a standard operation such as visual inspection, marking it as a Count Point ensures that its completion will be tracked and reported for all work orders referencing it. A Count Point operation is one where progress must be explicitly recorded, allowing visibility into work order completion.
Selecting the Count Point check box ensures that this operation becomes a mandatory checkpoint where users must report completion in all related work orders. This is essential for operations like visual inspection, where reporting completion is critical to production quality.


NEW QUESTION # 33
To help ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), your client wants to enable audit trail for manufacturing work definitions and standard operations.
Which is NOT included in the audit trail for standard operations such as creation, update, and deletion?

  • A. Attachments at any level
  • B. Descriptive flexfields (OFFs) at any level
  • C. Item structure component attributes referenced from Product Information Management(PIM)
  • D. Operation resources. Including alternate resources
  • E. Work definition header and version attributes

Answer: C


NEW QUESTION # 34
Which statement is NOT true about cumulative lead time?

  • A. It calculates cumulative manufacturing lead times by rolling up manufacturing lead times of make Items.
  • B. It calculates cumulative total lead times by rolling up lead times of make items and adding up lead time values of buy items.
  • C. It updates lead time percent at the operation level in the work definition.
  • D. It updates the item's lead time attributes at the end of the calculation process: cumulative manufacturing and cumulative total lead times.

Answer: C


NEW QUESTION # 35
You are implementing project-driven supply chain functionality. You need to set up movement requests to issue or transfer project material to manage the inventory associated with projects and tasks.
Which two are types of movement requests to issue or transfer project material?

  • A. Perform manual pick for such movement requests using the project material, common inventory, or inventory from another project.
  • B. Transfer project material from one subinventory to another.
  • C. Create o movement receipt line with the Project Costing widget.
  • D. Pick transactions Interfaced by the project costing project and task using the project material, common Inventory, or Inventory from another project.

Answer: A,B

Explanation:
When setting up movement requests in a project-driven supply chain, you need to manage inventory associated with specific projects and tasks. The two correct types of movement requests in this context are:
Statement A: Transfer project material from one subinventory to another - This is a standard type of movement request in Oracle Cloud, allowing project materials to be transferred between subinventories. It is essential for managing inventory tied to specific projects and tasks, ensuring that materials are available where needed for project execution.
Reference:
Statement D: Perform manual pick for such movement requests using the project material, common inventory, or inventory from another project - Manual picking for project-specific material is another supported operation. It allows users to perform manual picks from various sources, such as project material, common inventory, or even inventory from other projects.
Incorrect Statements:
Statement B: Pick transactions are not interfaced specifically by project costing. Although project costing is relevant for tracking costs, it is not the driving factor behind pick transactions.
Statement C: There is no concept of creating a movement receipt line with the "Project Costing widget" in Oracle Manufacturing Cloud.


NEW QUESTION # 36
Your client is planning to override the Plant Production Calendar with One or More Date-Effective Work Center Calendars. You need to explain the consideration when using the Override the Plant Production Calendar with One or More Date-Effective Work Center Calendars feature.
Which three statements are true when overriding the production calendar?

  • A. Supplier operations used in outside processing use the work center calendar in work order scheduling.
  • B. When the user executes search action in the Review Dispatch List page, if more than one work center are selected and if the start date or completion date is based on Shift-based search, then the operations are queried based on the shifts of the plant calendar only.
  • C. While defining override calendars, you need to ensure that the date effective range for a work center calendar association can be overlapping and contiguous.
  • D. The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars.
  • E. Even if there are override calendars, the lead time calculation in days for an item remains based on the plant calendar and not on work center calendars.

Answer: B,D,E

Explanation:
Overriding the plant production calendar with date-effective work center calendars provides flexibility in scheduling specific work centers with different operating hours. However, certain aspects of production planning and execution remain tied to the plant-level calendar. Here are the details:
Statement A: The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars - Even when work centers have their own calendars, the high-level overview and exception reporting remain based on the plant calendar.
Statement C: Lead time calculation in days for an item remains based on the plant calendar - Lead times are calculated using the plant calendar, regardless of work center-specific calendars, ensuring consistency in planning.
Statement D: Search actions in the Review Dispatch List page query operations based on the plant calendar shifts when multiple work centers are selected - For consistency in dispatching, the system references the plant calendar when shift-based search parameters are used across multiple work centers.
Incorrect Statements:
Statement B: Date-effective ranges for work center calendars should not overlap for accuracy in scheduling.
Statement E: Supplier operations in outside processing generally rely on the plant calendar for consistency unless explicitly configured otherwise.


NEW QUESTION # 37
In a manufacturing plant, two purchase components, PI and P2, and a resource, Rl, are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates for the assembly have been defined as Required.
A Cost Accountant is estimating cost of the assembly, and analyzing rolled-up costs before finally publishing estimates as frozen standards to Cost Accounting by using a Cost Planning Scenario. While reviewing rolled-up costs, the extended costs of purchase components are not included in a rolled-up scenario.
What is the reason for this?

  • A. Costs for purchase components PI and P2 are not defined In Cost Accounting.
  • B. Create Accounting Distributions was not initiated.
  • C. Purchase components PI and P2 are not associated with the material cost plan of the Cost Planning Scenario.
  • D. Create Accounting was not initiated.

Answer: C

Explanation:
In Oracle Manufacturing Cloud, when performing a cost analysis using Cost Planning Scenarios, all components and resources involved in the assembly must be associated with the material cost plan to be included in the rolled-up cost estimates. The reason the extended costs of purchase components (P1 and P2) are not included in the rolled-up scenario is that:
Purchase components PI and P2 are not associated with the material cost plan of the Cost Planning Scenario. This means that although the components are defined in the system, they haven't been linked to the cost planning scenario, so their costs are not included in the rolled-up calculations.
Incorrect options:
Costs for purchase components PI and P2 are not defined in Cost Accounting (A): While defining costs is necessary, the issue here is the components not being associated with the cost plan.
Create Accounting (C) and Create Accounting Distributions (D) are not relevant to the rolled-up scenario in this context, as they relate to the accounting process, not cost planning.


NEW QUESTION # 38
Which three are Cost accounting methods'

  • A. Perpetual Average Cost
  • B. Frozen Standard Cost
  • C. Layer Cost, also known as "LIFO"
  • D. Periodic Actual Cost
  • E. Actual Cost, also known as "FIFO"

Answer: A,B,E

Explanation:
Oracle Manufacturing Cloud supports multiple cost accounting methods to help organizations track the cost of their goods and inventory effectively. Below is an explanation of the correct answers:
Statement A: Perpetual Average Cost - This is a commonly used method in Oracle Cloud where the system continuously updates the average cost of an item with each receipt or transaction. This method is useful for organizations that need to track the moving average cost of goods in real-time.
Reference:
Statement C: Frozen Standard Cost - This method involves predefining a standard cost for each item at the beginning of a financial period. The cost remains "frozen" throughout the period, and variances between the actual cost and the standard cost are tracked and analyzed separately.
Statement D: Actual Cost, also known as "FIFO" - The FIFO (First In, First Out) method records costs based on the order in which items are received. It is a type of actual costing where items are valued based on the specific costs of the earliest received inventory. Oracle Cloud supports FIFO as part of its actual costing methods.
Incorrect Statements:
Statement B: Layer Cost, also known as "LIFO" - Oracle Cloud does not natively support LIFO (Last In, First Out) as a cost method due to accounting and regulatory restrictions in various regions. LIFO is generally not used in the system as a standard method.
Statement E: Periodic Actual Cost - While there is a method called Periodic Average Cost, Periodic Actual Cost is not typically listed as a standard costing method in Oracle Cloud.


NEW QUESTION # 39
Your client needs to implement operational checks for compliance with training and job requirements. Which four statements are true about this functionality?

  • A. You have the ability to associate a Job profile with a Work definition operation resource.
  • B. The qualification Is used to warn a production supervisor If they assign operators that don't meet the skill requirements against the resource.
  • C. A qualified operator need not be specified to report resource transactions.
  • D. You have the ability to associate a Job profile with a Standard operation resource.
  • E. You do not have the ability to associate a Job profile with a Work order operation resource.
  • F. The qualification Is enforced during reporting of labor usage.

Answer: A,B,D,F

Explanation:
Oracle Manufacturing Cloud provides functionality to enforce compliance with training and job requirements through operational checks. The correct statements are:
Statement B: You can associate a job profile with a work definition operation resource. This ensures that only operators who meet the job requirements are allowed to perform the work.
Statement C: Qualifications are enforced when reporting labor usage, meaning that if an operator lacks the required qualifications, the system can prevent or warn about the labor transaction.
Statement D: You can also associate a job profile with a standard operation resource to enforce skills and training compliance.
Statement F: If an unqualified operator is assigned to a task, the system can notify the production supervisor to avoid non-compliance with skill requirements.
Incorrect options:
Statement A: A qualified operator must be specified to report resource transactions.
Statement E: You can associate a job profile with a work order operation resource, contrary to what is implied.


NEW QUESTION # 40
......

LATEST 1z0-1075-24 Exam Practice Material: https://www.freecram.com/Oracle-certification/1z0-1075-24-exam-dumps.html

New 1z0-1075-24 Actual Exam Dumps,  Oracle Practice Test: https://drive.google.com/open?id=1dBueaV1t7PD27xmZickwK-q1YQQMrFvu

0
0
0
10