NEW QUESTION # 11
Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

  • A. The task rate cards.
  • B. The CI rate cards.
  • C. The hourly rate of the specified role.
  • D. The distribution costs

Answer: C

Explanation:
Explanation
According to the ServiceNow documentation1, when requesting resources from a group and when resource role is specified, the planned cost is calculated from the hourly rate of the specified role. The system uses the rate card associated with the resource plan to determine the hourly rate for each role. The other options are incorrect because:
A: The distribution costs: The distribution costs are the costs that are distributed across the project tasks based on the resource plan allocation2.
B: The task rate cards: The task rate cards are the rate cards that are applied to the project tasks, not the resource plan3.
D: The CI rate cards: The CI rate cards are the rate cards that are applied to the configuration items, not the resource plan4.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con


NEW QUESTION # 12
Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.

  • A. pm_toplevel_project
  • B. pm_project
  • C. pm_home_page_config
  • D. project_template_config

Answer: C

Explanation:
Explanation
According to the ServiceNow documentation1, the pm_home_page_config table is used to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace. The other tables are used for different purposes:
pm_project: Stores information about projects2.
pm_toplevel_project: Stores information about top-level projects3.
project_template_config: Stores information about project templates.


NEW QUESTION # 13
The Project management application supports two types of external dependencies. What are they?
Choose 2 answers

  • A. Soft Dependency.
  • B. Change Dependency.
  • C. Milestone Dependency.
  • D. Task Dependency.
  • E. Hard Dependency.

Answer: A,E

Explanation:
Explanation
The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in the Product Documentation for ServiceNow.


NEW QUESTION # 14
Demand assessments are triggered as soon as the demand enters what state?

  • A. Submitted.
  • B. Approved.
  • C. Qualified.
  • D. Screening.

Answer: A

Explanation:
Explanation
According to the Completing Demand Assessments document, demand assessments are triggered as soon as the demand enters the Submitted state. The other options are not correct, as demand assessments are not triggered when the demand is Approved, Screening, or Qualified.


NEW QUESTION # 15
What is the default table that stores the idea categories that a user can select from when submitting an idea?

  • A. im_module
  • B. dmn_demand
  • C. im_idea_core
  • D. im_category

Answer: D

Explanation:
Explanation
According to the Category Configuration document, the default table that stores the idea categories that a user can select from when submitting an idea is im_category. This table contains the predefined categories for ideas, such as Business Process, Customer Service, or IT Service. The other options are not correct, as they are not the tables that store the idea categories. The dmn_demand table stores the demand records that are created from the approved ideas. The im_module table stores the idea modules that are used to group ideas by different criteria. The im_idea_core table stores the core fields of the idea records.


NEW QUESTION # 16
Is resource capacity derived from FTE or schedules?

  • A. Neither.
  • B. Only FTE.
  • C. Both.
  • D. Only Schedules.

Answer: D

Explanation:
Explanation
Resource capacity is the total number of hours that a resource or a group of resources is available for work in a given time period. According to the Product Documentation for ServiceNow, resource capacity is derived from the user or group schedule, which defines the working hours and days for each resource. The group capacity is rolled up from the schedules of all the members. Note: Capacity is not derived from FTE, but from schedules. Both FTE and schedules must be in synchronization with each other. FTE is a measure of how much work a resource can perform in a standard work week, and it is used to calculate the resource demand and allocation.


NEW QUESTION # 17
The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?

  • A. Reference.
  • B. Conditions.
  • C. List.
  • D. Journal.

Answer: A

Explanation:
Explanation
According to the ServiceNow documentation1, the Business Unit field on a Project or Demand form is a reference field that displays values from the cmn_department table. A reference field stores a link to a record on another table, rather than storing the data directly in the field2.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/refer
https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/form-administration/con


NEW QUESTION # 18
If a sub-project and parent project have different project currencies, this property should be set to true for cost roll-ups.

  • A. com.snc.project.copy.additional_attributes
  • B. com.snc.project.rollup_project_start_date
  • C. com.snc.project.calculate_roi
  • D. com.snc.project.multicurrency.rollup_if_different

Answer: D


NEW QUESTION # 19
What features are not included in a teamspace application but can be added in teamspace settings? Choose 2 answers

  • A. Demand Assessments
  • B. Idea
  • C. Workbench configuration
  • D. Project

Answer: A,B

Explanation:
Explanation
According to the Teamspaces document, features such as idea and demand assessments are not included in a teamspace application by default, but can be added in teamspace settings. Idea is a feature that allows users to submit and vote on ideas for new or improved products, services, or processes. Demand assessments are a feature that allows users to evaluate the demands based on various criteria, such as strategic alignment, risk, and return on investment. The other options are not correct, as they are features that are included in a teamspace application by default. Workbench configuration is a feature that allows users to customize the workbench for the teamspace. Project is a feature that allows users to create and manage projects within the teamspace.


NEW QUESTION # 20
Which related lists should primarily be used to capture financial data in a project?
Choose 2 answers

  • A. Cost Plans
  • B. Monetary Benefit Plans
  • C. Risks
  • D. Programs

Answer: A,B

Explanation:
Explanation
Cost Plans and Monetary Benefit Plans are the related lists that should primarily be used to capture financial data in a project. Cost Plans allow you to define the expected costs of a project over time, based on the planned and actual work, resources, and expenses. Monetary Benefit Plans allow you to define the expected financial benefits of a project over time, based on the estimated and realized value, revenue, and savings. You can find more information about these related lists in the Product Documentation for ServiceNow.


NEW QUESTION # 21
To set up a group for selection in a resource plan, the group record needs to include which role?

  • A. pps_resource
  • B. itil
  • C. it_project_user
  • D. resource_manager

Answer: A

Explanation:
Explanation
According to the Assigning Resource Roles document, to set up a group for selection in a resource plan, the group record needs to include the pps_resource role. This role grants access to the Resource Management application and allows the group members to view and update their resource allocations. The other options are not correct, as they are not required for a group to be selected in a resource plan. The it_project_user role grants access to the Project Portfolio Management application and allows the user to create and update projects. The itil role grants access to the ITIL application and allows the user to manage incidents, problems, and changes. The resource_manager role grants access to the Resource Management application and allows the user to manage resource plans and allocations.


NEW QUESTION # 22
If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following?
Choose 2 answers

  • A. Program Workbench
  • B. Portfolio Planning related link
  • C. Project module
  • D. Portfolio Planning Workbench module

Answer: B,D

Explanation:
Explanation
According to the Scenario Planning for PPM document, a portfolio manager can access the Portfolio Planning Workbench by navigating to either the Portfolio Planning related link on the portfolio form or the Portfolio Planning Workbench module under the Portfolio Planning application menu. The other options are not correct, as they do not lead to the Portfolio Planning Workbench. The Project module is under the Project Portfolio Management application menu and the Program Workbench is under the Program Management application menu.


NEW QUESTION # 23
On the demand form, what does the Discount Rate impact?

  • A. Internal Rate of Return %.
  • B. Net Present Value (NPV).
  • C. Financial Benefit.
  • D. ROI.

Answer: B

Explanation:
Explanation
According to the ServiceNow documentation1, the discount rate on the demand form impacts the net present value (NPV) of the demand. The NPV is the difference between the present value of the benefits and the present value of the costs of the demand. The discount rate is the rate used to discount future cash flows to their present value. A higher discount rate means that future cash flows are worth less in the present, and vice versa. The other options are incorrect because:
A: ROI: The ROI (return on investment) is the ratio of the net value to the estimated cost of the demand. The discount rate does not affect the ROI, as both the net value and the estimated cost are based on the present value of the cash flows2.
C: Financial Benefit: The financial benefit is the sum of the present value of the benefits of the demand. The discount rate does not affect the financial benefit directly, but only indirectly through the NPV calculation3.
D: Internal Rate of Return %: The internal rate of return % (IRR) is the discount rate that makes the NPV of the demand equal to zero. The discount rate does not affect the IRR, but rather the IRR is derived from the NPV equation4.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/refe
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc


NEW QUESTION # 24
If a lens has four entities, which entity within the lens structure would not have a parent reference?

  • A. Top-level entity
  • B. Third-level entity
  • C. Bottom entity
  • D. Second-level entity

Answer: A

Explanation:
Explanation
According to the ServiceNow documentation1, a lens is a hierarchical structure that consists of entities and relationships. An entity is a data object that represents a business concept, such as a project, a demand, or a resource. A relationship is a link between two entities that defines how they are connected. A lens can have up to four levels of entities, each with a parent reference to the entity above it, except for the top-level entity, which has no parent reference. The top-level entity is the root of the lens and defines its scope and type. For example, a project lens has a project as the top-level entity, and a demand lens has a demand as the top-level entity.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/it-business-management/c


NEW QUESTION # 25
As a demand manager, you can view an artifact from a demand. What artifacts are part of a demand?

  • A. Stories, Vulnerability Tasks, Enhancements.
  • B. Project, Defect, Requests.
  • C. Incidents, Problems, Change.
  • D. Decision, Risk, Requirements.

Answer: D

Explanation:
Explanation
According to the ServiceNow documentation1, a demand manager can view and edit the following artifacts from a demand:
Decision: A decision that affects the demand or its outcome2.
Risk: A risk that could impact the demand or its outcome3.
Requirement: A requirement that defines the scope or functionality of the demand4.
The other options are not artifacts of a demand, but rather related entities that can be created from a demand or linked to a demand.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task


NEW QUESTION # 26
......

CIS-SPM Questions Truly Valid For Your ServiceNow Exam: https://www.freecram.com/ServiceNow-certification/CIS-SPM-exam-dumps.html

CIS-SPM Actual Questions - Instant Download Tests Free Updated Today!: https://drive.google.com/open?id=1RMNLv9Rz0jyHJGUQOTQ6Y3k9VKcL9Ger

0
0
0
10