Get Instant Access to L4M8 Practice Exam Questions
Reliable Study Materials & Testing Engine for L4M8 Exam Success!
NEW QUESTION # 41
What does the acronym SMART stand for?
Answer:
Explanation:
When the procurement professional is setting key performance indicator (KPI) where which the supplier performance will be monitored and managed. The KPI is expected to be SMART. SMART is an acronym that is used to set KPI and specification.
S - specific ,
M - measurable,
A - achievable,
R - relevant, and
T - timebound.
NEW QUESTION # 42
Explain how influencing, can relate to corruption within procurement.
Answer:
Explanation:
Influencing is the capacity to be able to change behavior or opinions, either consciously or subconsciously.
As outlined by Yukl and falbets work from 1990 influencing can relate to corruption within pro-curement in these six ways.
1)A party can be assertive (forceful, directive, using deadlines),
2) Ingratiating i.e. using charm and flattery.
3) Exchange-Trading favors,
4) Upward appeal (requesting input for senior management not only that influencing can come as
5) Coalition; team members uniting for support.
5) Rational persuasion, i.e. bringing in logic and facts for clarification.
NEW QUESTION # 43
Describe one implied term and one expressed term from a contract with which you are familiar.
Answer:
Explanation:
Terms are the right and duties agreed between parties which are then documented in contract. Terms can be implied or expressed.
Implied terms are always present in a contract and are set by national laws; implied terms do not have to be written or verbally agreed : they always exist, for example sales of Gods Act, good being fit for purpose, Negligence ,confidence , whereas expressed terms are negotiated and agreed rather than being automatically included, express terms are agreed between, parties negotiating the contract. For example; payment terms, specification, delivery details and quantities.
NEW QUESTION # 44
Explain which company you would award the contract to base on the weighted score card in table below.
Answer:
Explanation:
A weighted score card is a tool with a systematic and a fair process for selecting supplier, based on predetermined criteri a. This tool can help make the decision by presenting a fair display of how all suppliers did in the process. The values of these weights are based on their importance. The supplier with the highest score card is considered the most suitable to be awarded the contract.
In the table above, cost is considered more than all other criteria. Contract length is the lowest which is weighted 2 Base on the weighted score card as presented above, company B scored 78 while company A and company C scored 65 and 63 respectively.
Company A, having scored the highest (78) should be awarded the contract.
*
Refer to the question column for response
NEW QUESTION # 45
Which Incoterm applies here?
The supplier is responsible for delivering the goods to a point alongside a water vessel (such as a dock or quay) as determined by the buyer at a named port. Once delivered, all risk is transferred to the buyer until the goods are transported and delivered to their name destination.
- A. FAS - Free Alongside Ship
- B. DAT - Delivered At Terminal
- C. DAP - Delivered At Place
- D. DDP - Delivery Duty Paid
Answer: A
NEW QUESTION # 46
What are the reasons that a contract can legally be terminated?
Answer:
Explanation:
A contract is written or verbal agreement, made between two or more parties that are legally en-forceable. For a contract to be legally binding it must include intention of parties entering into the contracts. All parties must have the capacity to contract or be contracted. They must be of a sound mind, there should be a promise (offer) for performance from the other party and an exchange (consideration) of one thing for another within an agreement for contract to be binding, there must be an acceptance of the offeror's offer by the offeree.
There are many reasons contract can legally be terminated, including non-performance by one or both parties, a significant change in the requirement.
There are several reasons contract can legally be terminated, including non-performance by one or both parties; breach of material, failure to meet service level agreement, ethical breaches, a significant change in the requirement of either party caused by ethical change in the market, change in Demand, obsolescence, contract completion. The procurement professionals should get an exit strategy that should encourage a stress free disengagement should incase there are no profitable reason to continue with the contract.
NEW QUESTION # 47
What two areas of an organization do the Kraljic Portfolio matrix uses to establish the category of a product or service?
Answer:
Explanation:
The Kraljic Portfolio Matrix shows where a product or services fits into in an organization. It is based on two areas 1) the risk of supply (Risk Impact). 2) Effect it has on profit (cost impact).
NEW QUESTION # 48
What is business case?
Answer:
Explanation:
A business case is a document containing the justification and the commercial benefits achievable for a potential project or an identified need, for example, the purchase of a capital equipment, con-struction of an additional warehouse or procuring more innovative software to replace the current on in use.
The essence of the business case is to obtain support and get buy-in from senior management.
In order to gain authority to apply whole life asset management a business case will need to be created and presented. A developed business case will cover the following element.
1) Introduction: Outline of what the business case is all about
2) Objective: Explanation of what the business case desired outcome is.
3) Approach that will be undertaken
4) List of resources required
5) Benefits of achieving the objective
NEW QUESTION # 49
Describe a situation where amendment or an addendum would need to be created
Answer:
Explanation:
After all the due diligence is carried out, before awarding contract to the best supplier, sometimes procurement professionals find themselves in some problem solving situation; this might have been emanated from supplier facing a financial challenge or problems from external environment. Responding to this might require an amendment or an addendum, depending on the case in hand.
An amendment is for a physical change in the existing contract for example; if a contract contains a negotiated and agreed fixed price for the period of the contract but unexpected market forces such as an economic down turn or force majeure occur, the supplier may have to request an amendment order to continue to make a profit.
An addendum is when an additional document is added to the existing contract for example, If a contract have a schedule of rates and the market forces prices up, an addendum can be added to an existing contract with a revised schedule. Once accepted, the addendum becomes part of the con-tract. Addendum are physically used when the forecasted cost of a project rises and approval is needed to increase the contract spend.
NEW QUESTION # 50
Use the balance sheet below to work out the correct ratio for coffee Time and explain whether the company appears to have enough assets to cover it liability.

Answer:
Explanation:
The current ratio is one of the two was to determine organizations liquidity (how quickly its assets can be converted into cash)
A current ratio of 1 shows that the organization has enough assets to repay (cover) it liability Buyers can be encouraged to deal with these suppliers after if they considered proven and strong in other areas.
NEW QUESTION # 51
Explain why you think quality should be investigated before working with potential supplier?
Answer:
Explanation:
Quality is fitness for purpose. It is important that quality is investigated by procurement professionals before forming relationship with potential supplies.
If quality is not investigated before selecting supplier the organization might stand the risk of facing the following disadvantages; Reputational Damages Cost of Rework Cost of Downtime Cost of Material Cost of being stocked with the wrong supplier Cost of being stocked in a project that may not come to an end at the forecasted time.
How buyer can choose a supplier with a good quality culture is first by defining the quality of the product or services to be carried out .Having knowledge of the product or service quality, supplies can rightly select and evaluated supplier with total quality management (TQM) in their system, ISO 9001 accreditation. TQM includes everyone in the organization with knowledge on the required quality; there would be little or no rejection/reworks. Thus is an added value to the organization.
NEW QUESTION # 52
Write all of factors that contribute towards value for a product that you regularly purchase.
Answer:
Explanation:
Factors that contribute towards value for clothe gum in a fashion firm;
1) How much money does the gum cost?
2) How much is the benefits of using the clothe gum?
3) Does customers prefer clothe gum at the bottom of their garment?
4) Is the clothe gum difficult to use?
5) Does the clothe gum beautifies the fabric when placed properly?
6) Does it give a better finishing?
7) Is it ethical to use?
8) Is it from a sustainable source?
9) is it environmental friendly?
10) Does using clothe gum suggest innovation in fashion?
NEW QUESTION # 53
Describe three ways in which a buyer could or test the market in other to assist with determining a need.
Answer:
Explanation:
Once the need has been understood, defined, justified and authorized, the next stages are to analyze and test the market. Analyzing and testing the market includes looking at the following
1. STEEPLE analysis
2. SWOT analysis
3. Porter's five forces
4. Level of suppliers competition
5. Supply and demand
6. Push and pull
7. Supplier segmentation
8. Product life cycle
9. Ansoff matrix
10. Early supplier involvement
11. Make or buy
12. Offshoring
1. Porter's five forces: The use of porter's five forces helps the procurement professional to understand the level of competition within the marketplace. Whether it is a monopoly, oligopoly, imperfect or perfect market. Knowing these will equip the organization to better negotiate a favorable price.
2. Supply and Demand: the procurement professional must also think about supply and demand as part of their market analysis when they receive a requisition. This economic factor has a significant effect on the prices charged and on the cost incurred.
3. Supplier segmentation: in this the procurement professional start to form an opinion of potential suppliers.. They can segment current suppliers into four categories, depending on their level of integration into an organization. This can help to inform the procurement professional of which type of supplier relationship that would be most appropriate.
NEW QUESTION # 54
What are the eight elements of whole life asset management?
Answer:
Explanation:
Whole life asset management is the process of evaluating the total price and all associated costs of a product to make an informed decision as to which option will provide the organization with the best value for money option: To achieve this the organization works at the following eight elements.
1. Identify need/objectives/risk: The first stage of the whole life asset management is the same as the first stage in the CIPS procurement and supply cycle: identify the need prior to any asset being procured; the need could be competition in the marketplace, raised/reduced demands or financial concern. Once this need has been identified, the objectives of the new assets need to be set, and this may include being more energy efficient, reducing cost or saving money.
Risk also needs to be explored. When investing in a new asset there are factors to be considered that may or may not be advantageous to the investment. These include; downtime, lost sale/revenue or associated cost.
2. Procurement: Procurement professional would have to source and arrange supply of the asset.
3. Construction: ones the supply has being arranged, then the designing and the manufacturing of the asset begins.
4. Commissioning
5. Deterioration/maintenance
6. Condition performance monitoring
7. Decommissioning
8. Renewal/replacement
NEW QUESTION # 55
Think of a supply chain with which you are familiar and distinguish between the primary, second-ary and tertiary sector organization within it.
Answer:
Explanation:
Supply chain involves a network of individuals, organizations, technology activities and resources to make sure goods or services flow along the chain. If one point fails, every part further along the chain fails.
Fullpower projects (a flour manufacturer) supply chain begins with producers (raw materials, wheat farmers), suppliers, manufactures, distributors, retailers and end users (customer).
Fullpower projects supply chain falls within the primary sector (producers of wheat), the secondary sector include the manufacturing (those that converts the wheat the suppliers brings into flour) and tertiary sector (the distributor those that takes the wheat to the end users).
NEW QUESTION # 56
Describe one qualitative and one quantitative measures of social impact for an organization with which you are familiar.
Answer:
Explanation:
Information gathered in relation to social impact for an organization is both qualitative and quantitative.
Fullpower consult is a project/procurement training company that has gotten a measure of its social impact.
The qualitative measure of the organization is its stakeholders perception. Stakeholders knows that fullpower will do all it can to always give the best value for money.
Fullpower has the policies to give 10% of its profit share back to the community, by sponsoring free trainings for both professionals and vocational.
Addition
Qualitative and quantitative measures of social impact
Qualitative
Stakeholder perception
Reputation
Good Ethical practice
Benefit to the economy
Quantitative
20% Reduction in emission
Amount of funding donated
Amount of train courses delivered
Percentage of Resources Replaced
*
Refer to the question column for response
NEW QUESTION # 57
Describe five types of contract terms that a procurement professional should create with a supplier when forming an agreement.
Answer:
Explanation:
Terms are the right and duties agreed which are then documented in a contract. Five types of con-tract terms that a procurement professional should create with a supplier when forming an agree-ment includes; Price term is when the buying organization wants to protect its budged and spending, it include price terms in the contract, for the buyer to buy goods or services in response to a need they some-time enshrine a bespoke specification in the contract.
Payment Term is to specify when and how the buyer will pay the supplier. The buyer may include a payment term in the contract.
Warrantee is when the buyer requires a promise from the supplier that the product or service will meet the specified need in the contract.
Time is of the essence term is included in the contract to detail when a product or service should be delivered and explains the potential losses of business if time is not observed.
NEW QUESTION # 58
What is contract performance review and continuous improvement?
Answer:
Explanation:
Contract performance review and continuous improvement is the stage 11 of the CIPS procurement and supply cycle.
In order to effectively manage supplier performance and contractual obligations, the suppliers per-formance against key performance indicators (KPI) should be reviewed regularly. This KPI should have been agreed doing the post contract award negotiation. In addition to review KPIs suppliers and the procurement team should work towards continuous improvement. This is a continuous ef-fort to improve product or services within an organization. This may involve improving quality, reducing waste in the supply chain and focusing on innovation. It is an ongoing process that works toward perfection.
NEW QUESTION # 59
What Incoterm applies here?
The goods are considered 'delivered' at the point of release from the supplier's premises or another name place. The supplier is not responsible for loading or transporting the goods and does not have to arrange export clearance - this must be arranged by the buyer. The risk is on the buyer from this point.
a) EXW - Ex Works
b) FCA - Free Career
c) CPT - Carriage Paid To
d) CIP - Carriage and Insurance Paid to
- A. EXW - Ex Works
- B. FCA - Free Career
- C. CPT - Carriage Paid To
- D. CIP - Carriage and Insurance Paid to
Answer: A
NEW QUESTION # 60
The supplier is responsible for delivering the goods to a named port or destination (such as an air-port or warehouse), as well as unloading them from the terminal from this point, risk passes to the buyer.
- A. FAS - Free Alongside Ship
- B. DAT - Delivered At Terminal
- C. DAP - Delivered At Place
- D. DP - Delivery Duty Paid
Answer: B
NEW QUESTION # 61
What happens in the public sector, regarding providing feedback?
Answer:
Explanation:
A sector is an area of an industry, e.g., private, public or third sector.
A public sector is a sector of the economy that is owned, finance and run by the government. This sector is financed with tax payer's money. And therefore owe the general public an ethical explanation towards all investment and decision.
Once the supplier that is awarded the contract has accepted, the buyer can tell the unsuccessful bidders. This usually happens through email or letter. The public sector is more likely to give feedback to unsuccessful bidders and also have to respond to any stakeholders that request information on why a supplier is not successful.
NEW QUESTION # 62
......
Validate your Skills with Updated L4M8 Exam Questions & Answers and Test Engine: https://www.freecram.com/CIPS-certification/L4M8-exam-dumps.html
Tested & Approved L4M8 Study Materials Download: https://drive.google.com/open?id=1u8dOtiRTjiS1Mrv_3V9gcT_5yfIFZIZj