The PR2F exam covers key principles, concepts, themes, and processes associated with the PRINCE2 methodology. It is designed to assess a candidate's understanding of the methodology and their ability to apply it in real-world scenarios. PRINCE2Foundation exam consists of 60 multiple-choice questions and lasts for 60 minutes. Candidates need to score at least 55% to pass the exam and obtain the certification.
PRINCE2 Foundation exam is an entry-level certification that is suitable for anyone who wants to learn about project management and the PRINCE2 methodology. It is ideal for project managers, team leaders, and anyone involved in managing projects. PRINCE2 7 Foundation written Exam certification is recognized globally and is highly valued by employers. Passing the PRINCE2 Foundation exam is an excellent way to demonstrate your knowledge and understanding of project management and increase your chances of landing a job in the field.
NEW QUESTION # 137
Which is a purpose of a quality register?
- A. To provide the status of quality activities carried out for completed products
- B. To record cross-references to issues relating to the quality of the products
- C. To capture quality concerns about completed products
- D. To record the date a completed work package was received
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 138
Which is one of the six aspects of project performance to be managed?
- A. Estimate
- B. Timescales
- C. Efficiency
- D. Work
Answer: B
Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/
Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets
NEW QUESTION # 139
Which is NOT obtained from a product's Product Description?
- A. The development method to be used
- B. The qualitymethod to be used
- C. The product's quality criteria
- D. Who will approve the product
Answer: A
NEW QUESTION # 140
Which is NOT included in the PRINCE2 definition of a project?
- A. A project'spurpose is to deliver one or more business products
- B. A project is based on an agreed Business Case
- C. A project is part of business as usual'
- D. A project is a temporary organization
Answer: C
NEW QUESTION # 141
Which is an objective of the quality review technique?
- A. To identify a product's quality criteria
- B. To assess that a product conforms to set criteria
- C. To ensure that staff are properly trained in the quality methods
- D. To provide assurance that the project is being conducted properly
Answer: B
NEW QUESTION # 142
Which is a purpose of the Directing a Project process?
- A. Establish the level of control required by the Project Board after initiation.
- B. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
- C. Provide the information required to confirm if it is worthwhile to initiate a project
- D. Enable overall control of a project to be exercised by the Project Board
Answer: D
Explanation:
The purpose of the Directing a Project process in PRINCE2 is to enable the Project Board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This ensures that the Project Board can make key decisions and remain accountable for the project's success while not being involved in the lower-level, day-to-day activities. References: PRINCE2 Foundation manual, PRINCE2 official resources
NEW QUESTION # 143
Which is a responsibility of a risk owner?
- A. Identify risks to the project that might occur in their department
- B. Determine project risk appetite
- C. Manage, monitor and control all aspects of an assigned risk
- D. Own and authorize the use of the risk budget to fund risk responses
Answer: C
NEW QUESTION # 144
Which statement describes the 'Implement' step within the recommended risk management procedure?
- A. Assess the proximity of a risk
- B. Implement the responsibilities for risks defined in the Risk Management Strategy
- C. Take planned action to respond to a risk
- D. Identify the level of risks that can be tolerated by the project
Answer: C
Explanation:
Section: Volume B
NEW QUESTION # 145
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Controlling a Stage
- B. Managing a Stage Boundary
- C. Starting up a Project
- D. Directing a Project
Answer: A
NEW QUESTION # 146
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
- A. benefits, quality, risk,
- B. change, quality, risk,
- C. benefits, change, quality,
- D. benefits, change, risk,
Answer: A
NEW QUESTION # 147
Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.
- A. status accounting
- B. exception planning
- C. stakeholder engagement
- D. risk assessment
Answer: A
NEW QUESTION # 148
Which describes risk appetite?
- A. An organization's unique attitude towards risk-taking
- B. A common set of risk categories, risk scales and evaluation techniques
- C. The budget set aside for potential changesto the scope of the project
- D. The risks to the expected benefits
Answer: A
NEW QUESTION # 149
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
- A. When a change is raised
- B. In exception situations
- C. At the start of the project
- D. Throughout each stage
Answer: D
Explanation:
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/
NEW QUESTION # 150
Which is a minimum requirement for applying the quality theme?
- A. To define the project's approach to quality assurance
- B. To appoint external reviewers for quality reviews
- C. To provide administrative support for quality controls
- D. To define quality criteria in product descriptions
Answer: A
NEW QUESTION # 151
What process aims to ensure accurate progress information is provided to the Project
Manager?
- A. Managing a Stage Boundary
- B. Managing Product Delivery
- C. Starting up a Project
- D. Directing a Project
Answer: B
NEW QUESTION # 152
Which term is defined as the means by which an organization transitions from its current state to the target state?
- A. change control
- B. Risk management
- C. Progress management
- D. Change management
Answer: D
Explanation:
Change management is defined as the means by which an organization transitions from its current state to the target state. It encompasses all activities involved in managing change, including handling changes to the scope of projects and ensuring that changes are implemented smoothly and sustainably. This involves strategic planning, oversight, and ensuring that changes are accepted and adopted by all stakeholders.
References: PRINCE2 Foundation training materials and glossary.
NEW QUESTION # 153
When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.
Which principle is being applied by the project manager when reviewing this information?
- A. Tailor ta Suit the project
- B. Ensure continued business justification
- C. Learn from experience
- D. Manage by stages
Answer: C
Explanation:
The principle of 'Learn from experience' in PRINCE2 mandates that project teams should continuously use previous lessons to improve the outcomes of current and future projects. By reviewing end project reports from similar past projects to understand and correct underestimations, the project manager is directly applying this principle to refine and optimize project planning and execution.References: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation
NEW QUESTION # 154
Which should be provided by a project mandate?
- A. Terms of reference
- B. Initiation Stage Plan
- C. Detailed Business Case
- D. Stage tolerances
Answer: A
NEW QUESTION # 155
Which is a benefit of using PRINCE2?
- A. It prevents any changes once the scope of a project has been agreed
- B. It includes techniques for critical path analysis and earned value analysis
- C. It enables a project manager to be accountable for the success of a project
- D. It promotes consistency of project work and the ability to reuse project assets.
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 156
Which is a responsibility of a risk owner?
- A. Identify risks to the project that might occur in their department
- B. Determine project risk appetite
- C. Manage, monitor and control all aspects of an assigned risk
- D. Own and authorize the use of the risk budget to fund risk responses
Answer: C
NEW QUESTION # 157
Identify the missing ward in the following sentence.
PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.
- A. project management team structure
- B. project bard
- C. project assurance
- D. project team
Answer: D
Explanation:
In PRINCE2, the term 'project team' encompasses all individuals who are allocated time and responsibilities on the project, covering both the project management team and the wider team members who work on the project's tasks. This terminology includes everyone contributing to the project's delivery.References: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation
NEW QUESTION # 158
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
- A. Project Plan
- B. Stage Plan
- C. Team Plan
- D. Benefits Review Plan
Answer: B
Explanation:
During the Managing a Stage Boundary process, the Stage Plan for the next stage is created and submitted for approval. This plan outlines the work to be done in the upcoming stage and is a critical element for Project Board review before the next stage can commence. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
NEW QUESTION # 159
Which is an assumption about the PRINCE2 customer/supplier environment?
- A. The supplier will pay for the project
- B. The customer will specify the desired result
- C. The customer will provide the resources to deliver the products
- D. The supplier will tailor the project's application of PRINCE2
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION # 160
Whose approval is needed to replace a Stage Plan with an Exception Plan?
- A. Project Board
- B. Team Manager
- C. Project Manager
- D. Corporate or programme management
Answer: A
NEW QUESTION # 161
Which is a purpose of a Project Product Description?
- A. Provides a list of all the products to be delivered by the project
- B. Defines what the project must deliver in order to gain acceptance
- C. Shows the dependencies between the project's products to aid planning
- D. Records the costs and timescales for delivery of the project's final product
Answer: B
Explanation:
Section: Volume B
NEW QUESTION # 162
......