NEW QUESTION # 41
What is the name of the evolutionary stage in a company's development in which an organisation overcomes the burden of bureaucracy through the use of interpersonal communication and the introduction of a new organisational design such as a matrix structure?
- A. direction evolution
- B. co-ordination evolution
- C. collaboration evolution
- D. creative evolution
Answer: C
Explanation:
InGreiner's growth phases, thecollaborationphase addresses bureaucratic overload usingteamwork, interpersonal collaboration, and flexible structures (e.g., matrix). It follows creative # direction # delegation # coordination #collaboration.
Reference:CIPS L5M8 Study Guide, p.105.
NEW QUESTION # 42
In the MBTI, the _____ dimension relates to the manner in which you gather information.
- A. Judgement/Perception
- B. Thinking/Feeling
- C. Sensation/Intuition
- D. Extrovert/Introvert
Answer: C
NEW QUESTION # 43
A large unpredicted event has occurred in the external environment which has affected Company X. Which of the following change responses would be most appropriate to this situation?
- A. incremental-proactive change
- B. incremental-reactive change
- C. proactive-transformational change
- D. reactive-transformational change
Answer: D
Explanation:
Alarge, already-occurred external eventcalls forreactiveresponse; given its magnitude, the change must be transformationalrather than incremental.
Reference:CIPS L5M8 Study Guide, p.124.
NEW QUESTION # 44
In Project Management, what roles does theBoard/Steering Groupperform?Select TWO
- A. authorises the initiation of the project
- B. approves major deviations from the original plan
- C. replaces ineffective team members within the project group
- D. approves a budget to the project
Answer: A,B
Explanation:
TheBoard/Steering Grouphas ultimate accountability; itauthorises initiationandapproves major decisions
/deviationsduring delivery. Budgeting and staffing are typically managed via other governance routes/roles.
Reference:CIPS L5M8 Study Guide, p.161.
NEW QUESTION # 45
The business case includes information on _____.
- A. the project objective, high-level requirements, and time and cost goals
- B. relevant government or industry standards
- C. policies, procedures, guidelines, and systems that influence a project,s success
- D. the business need for the project
Answer: A
NEW QUESTION # 46
Key outputs of _____ process are project staff assignments, resource calendars, and project management plan updates.
- A. acquiring the project team
- B. developing the project team
- C. planning the human resource plan
- D. managing the project team
Answer: A
NEW QUESTION # 47
The role of a _____ is to provide direction and funding for a project.
- A. project sponsor
- B. project manager
- C. support staff member
- D. project team
Answer: A
NEW QUESTION # 48
One of the main outputs of the _____ process is a cost baseline.
- A. cost planning
- B. cost estimating
- C. cost budgeting
- D. cost controlling
Answer: C
NEW QUESTION # 49
_____ involves deining which risks are likely to affect a project and documenting the characteristics of each.
- A. Performing quantitative risk analysis
- B. Identifying risks
- C. Performing qualitative risk analysis
- D. Planning risk management
Answer: B
NEW QUESTION # 50
Dependencies are the relation between tasks and dictate the order in which tasks are approached. Claudia is running a tender under the Public Contracts Regulations 2015, and there is a 10-day standstill period before she can draft the contract. What type of dependency is this?
- A. discretionary dependency
- B. external dependency
- C. mandatory dependency
- D. internal dependency
Answer: C
Explanation:
Amandatory dependencyislegally or logically required- in this case, the statutory 10-day "standstill" under public procurement law. Other types:external(outside factors),discretionary(team choice),internal (organisational processes).
Reference:CIPS L5M8 Study Guide, p.220.
NEW QUESTION # 51
A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.
- A. False
- B. True
Answer: B
NEW QUESTION # 52
What is the role of theExecutiveof a Project Board?Select THREE
- A. manages conflicts of interest
- B. promotes the desired user outcomes
- C. acts as a single point of accountability
- D. represents those that design and develop the project products
- E. appoints other members to the board
Answer: A,C,E
Explanation:
TheExecutiveserves as thesingle point of accountability,manages conflicts of interest, andappoints board members.Senior Userpromotes user outcomes;Senior Supplierrepresents designers/developers.
Reference:CIPS L5M8 Study Guide, p.164.
NEW QUESTION # 53
An organizational culture with strong unit integration makes the project manager's job more difficult.
- A. False
- B. True
Answer: A
NEW QUESTION # 54
What is meant by "resource levelling"?
- A. adjusting project resources based on demand and supply
- B. employing a set number of people on a project from start to finish
- C. employing the same number of people on each concurrent project
- D. back-loading resources to a project
Answer: A
Explanation:
Resource levellingadjusts resource allocations to balancedemand vs. capacity constraintsover time (adding when workload peaks; releasing when it ebbs) to reduce bottlenecks.
Reference:CIPS L5M8 Study Guide, p.47.
NEW QUESTION # 55
Monika has created a Goal Grid to map the goals and objectives of a change she wishes to implement in the Procurement Department. The Grid has 4 categories, what would these be?
- A. continue, cease, improve, avoid
- B. review, direct, initiate, stop
- C. strengths, weaknesses, opportunities, threats
- D. achieve, preserve, avoid, eliminate
Answer: D
Explanation:
TheGoal Griddistinguishes whether outcomes are good/bad and whether they already exist or not, yielding four categories:Achieve, Preserve, Avoid, Eliminate.
Reference:CIPS L5M8 Study Guide, p.141.
NEW QUESTION # 56
Process improvement plan, quality metrics, and quality checklists are the outputs of the _____ process of project quality management.
- A. controlling quality
- B. planning quality management
- C. performing quality assurance
- D. quality certification
Answer: B
NEW QUESTION # 57
Raincoat Incorporated is running a project with two major activities. Activity 1 will start on the 1st January and finish on the 1st June. Activity 2 will start just before the completion of Activity 1, around 15th May, and run until 31st December. What type of sequencing is being used?
- A. start to finish with lead
- B. start to finish with lag
- C. finish to start with lead
- D. finish to start with lag
Answer: C
Explanation:
This isFinish-to-Start with Lead: Activity 2 begins slightlybeforeActivity 1 ends (overlap).Lagwould indicate a delay or gap;leadindicates an early start/overlap.
Reference:CIPS L5M8 Study Guide, p.220.
NEW QUESTION # 58
In organizational culture, people focus refers to _____.
- A. the degree to which management,s decisions take into account the effect of outcomes on employees within the organization
- B. the degree to which rules, policies, and direct supervision are used to oversee and control employee behavior
- C. the degree to which the organization monitors and responds to changes in the external environment
- D. the degree to which employees are encouraged to be aggressive, innovative, and risk seeking
Answer: A
NEW QUESTION # 59
Rachel is the Executive of a Project Board and is tasked with creating a Project Initiation Document (PID).
Which of the following is TRUE about this document?Select TWO
- A. it includes only the positive aspects of the project such as what the project will achieve
- B. it is created once at the beginning of the project and reviewed at the end
- C. it includes both positive and negative aspects of the project including constraints and risks
- D. it is created before the project takes place but can be edited during the project
Answer: C,D
Explanation:
APIDis produced before delivery but can beupdatedas the project evolves. It should coverscope, objectives, constraints, risks, assumptions-i.e., bothpositive and negativeaspects.
Reference:CIPS L5M8 Study Guide, pp.170-172.
NEW QUESTION # 60
_____ refers to a set of shared assumptions, values, and behaviors that characterize the functioning of an organization.
- A. organizational structure
- B. organizational culture
- C. chain of command
- D. line of control
Answer: B
NEW QUESTION # 61
Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project.
- A. False
- B. True
Answer: B
NEW QUESTION # 62
Which of the following is true of push communication?
- A. Information is sent to recipients without their request.
- B. This method ensures that the information is understood by recipients.
- C. This method ensures that the information is received by the recipients.
- D. Information is sent only to recipients who request the information.
Answer: A
NEW QUESTION # 63
The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks.
- A. top-down
- B. mind mapping
- C. bottom-up
- D. analogy
Answer: B
NEW QUESTION # 64
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?
- A. Sequencing activities
- B. Estimating activity durations
- C. Defining activities
- D. Planning schedule management
Answer: A
NEW QUESTION # 65
It is extremely important to document any changes in technical specifications that might affect product performance.
- A. False
- B. True
Answer: B
NEW QUESTION # 66
......
Try Best L5M8 Exam Questions from Training Expert FreeCram: https://www.freecram.com/CIPS-certification/L5M8-exam-dumps.html
Practice Examples and Dumps & Tips for 2026 Latest L5M8 Valid Tests Dumps: https://drive.google.com/open?id=17GlMgnE4LtEJbyzNzdX408imjqGIFNmx