Under what circumstances should a competitive tender not be completed? Select TWO.

Suggested Answer: B,D Vote an answer

Note the word 'NOT' in the question. In order for a competitive tender to be successful, there should be a clear specification in place (i.e. you need to know what you want, in order for suppliers to bid for it). Competitive tendering should also only be used for high value purchases; it's time consuming to do, so you wouldn't do it for low value items such as pens for the office. Therefore the correct answer to this question is 'items are of low value' and 'there isn't a clear specification'. There's a useful table on p.73 of when you would and wouldn't use a competitive tender.

by Jo at Jun 17, 2024, 02:58 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10