Exam IIA-CIA-Part2 Topic 5 Question 445 Discussion
Actual exam question for IIA's IIA-CIA-Part2 exam
Question #: 445
Topic #: 5
Question #: 445
Topic #: 5
In an organization with a large internal audit activity that has several audit teams performing engagements simultaneously which of the following tasks is an engagement supervisor most likely to perform during the planning phase of a new engagement?
Suggested Answer: B Vote an answer
During the planning phase of a new engagement, an engagement supervisor is responsible for ensuring that the engagement is designed effectively to meet its objectives. One of the critical tasks involves approving the engagement work program. The work program outlines the detailed steps and procedures that the audit team will follow during the engagement. By approving this program, the supervisor ensures that it is comprehensive, aligned with the engagement objectives, and capable of addressing identified risks and controls effectively. This step is essential to ensure that the engagement is conducted systematically and covers all necessary areas.
References:
* The Institute of Internal Auditors (IIA) Standard 2200: Engagement Planning
* IIA Practice Advisory 2200-1: Engagement Planning Considerations
References:
* The Institute of Internal Auditors (IIA) Standard 2200: Engagement Planning
* IIA Practice Advisory 2200-1: Engagement Planning Considerations
by Craig at Sep 08, 2025, 01:01 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).