Which of the following is the PRIMARY reason to conduct a cost-benefit analysis as part of a risk response business case?
Suggested Answer: A Vote an answer
The primary reason for a cost-benefit analysis in a risk response business case is to determine whether the reduction in risk achieved by the response justifies the cost of implementing it. It's about weighing the potential benefits (reduced risk) against the costs of the response.
While determining future resource requirements (B) and calculating ROI (C) can be part of the analysis, the primary focus is on justifying the cost based on risk reduction.
While determining future resource requirements (B) and calculating ROI (C) can be part of the analysis, the primary focus is on justifying the cost based on risk reduction.
by Claire at Aug 10, 2026, 06:24 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).