What is a standardized, effective, and efficient way to manage changes to project documentation?
Suggested Answer: C Vote an answer
Explanation
A configuration management system is a standardized, effective, and efficient way to manage changes to project documentation. A configuration management system is a set of tools and processes that help to track, control, and update the configuration items (CIs) of a project, such as documents, requirements, designs, code, tests, etc. A configuration management system helps to ensure that the project documentation is consistent, accurate, and up-to-date throughout the project life cycle. It also helps to maintain the traceability and auditability of the changes made to the project documentation. A configuration management system typically includes the following components:
A configuration management plan that defines the scope, roles, responsibilities, policies, procedures, and standards for configuration management.
A configuration management database (CMDB) that stores the information about the CIs, their attributes, relationships, versions, baselines, and changes.
A configuration identification process that assigns unique identifiers and names to the CIs and their versions.
A configuration control process that evaluates, approves, and implements changes to the CIs and their versions.
A configuration status accounting process that records and reports the status and history of the CIs and their versions.
A configuration verification and audit process that verifies and validates the CIs and their versions against the requirements and specifications.
References: = PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline, page 13.
A configuration management system is a standardized, effective, and efficient way to manage changes to project documentation. A configuration management system is a set of tools and processes that help to track, control, and update the configuration items (CIs) of a project, such as documents, requirements, designs, code, tests, etc. A configuration management system helps to ensure that the project documentation is consistent, accurate, and up-to-date throughout the project life cycle. It also helps to maintain the traceability and auditability of the changes made to the project documentation. A configuration management system typically includes the following components:
A configuration management plan that defines the scope, roles, responsibilities, policies, procedures, and standards for configuration management.
A configuration management database (CMDB) that stores the information about the CIs, their attributes, relationships, versions, baselines, and changes.
A configuration identification process that assigns unique identifiers and names to the CIs and their versions.
A configuration control process that evaluates, approves, and implements changes to the CIs and their versions.
A configuration status accounting process that records and reports the status and history of the CIs and their versions.
A configuration verification and audit process that verifies and validates the CIs and their versions against the requirements and specifications.
References: = PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline, page 13.
by Genevieve at Sep 10, 2024, 08:00 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).