Which is a FALSE statement about technical stages?
Suggested Answer: C Vote an answer
The statement that technical stages include the Managing a Stage Boundary process activities is false.
Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery. References: PRINCE2 Foundation manual, PRINCE2 official resources
Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery. References: PRINCE2 Foundation manual, PRINCE2 official resources
by Hugh at May 22, 2026, 11:31 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).