Exam PRINCE2-Foundation Topic 2 Question 330 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 330
Topic #: 2
Which is a FALSE statement about technical stages?

Suggested Answer: C Vote an answer

The statement that technical stages include the Managing a Stage Boundary process activities is false.
Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery. References: PRINCE2 Foundation manual, PRINCE2 official resources

by Hugh at May 22, 2026, 11:31 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.