Exam PRINCE2Foundation Topic 2 Question 283 Discussion

Actual exam question for PRINCE2's PRINCE2Foundation exam
Question #: 283
Topic #: 2
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used

Suggested Answer: D Vote an answer

Both Quality Assurance and Project Assurance are independent of the project manager, and they both ensure that applicable standards are used in the project. Quality Assurance is typically an external function that checks the project is using the right processes, while Project Assurance is internal to the project and provided by the project board, ensuring that the project continues to align with its objectives and the organizational environment. References: PRINCE2 7 Foundation Handbook and official training materials.

by Mandy at Apr 12, 2026, 07:14 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10