Exam Development-Lifecycle-and-Deployment-Architect Topic 1 Question 12 Discussion
Actual exam question for Salesforce's Development-Lifecycle-and-Deployment-Architect exam
Question #: 12
Topic #: 1
Question #: 12
Topic #: 1
Universal Containers is building a custom application on the Force.com platform. There is abudget and release date that has been set by the board of directors, but the application must meet the requirements that will be submitted and voted on by a public user community. What is the risk associated with the scenario?
Suggested Answer: D Vote an answer
Explanation
This is the correct answer because it is a risk to have a fixed release date and budget, but unknown and changing requirements. This may lead to unrealistic expectations, scope creep, and poor quality of the application. The requirements should be solicited by an external community if they are the end users or stakeholders of the application. The project can use either the waterfall or agile methodology, depending on the nature and complexity of the project, but the methodology should be aligned with the requirements and the release date.
This is the correct answer because it is a risk to have a fixed release date and budget, but unknown and changing requirements. This may lead to unrealistic expectations, scope creep, and poor quality of the application. The requirements should be solicited by an external community if they are the end users or stakeholders of the application. The project can use either the waterfall or agile methodology, depending on the nature and complexity of the project, but the methodology should be aligned with the requirements and the release date.
by Astrid at Nov 19, 2026, 06:06 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).