Exam Mule-101 Topic 5 Question 51 Discussion
Actual exam question for Salesforce's Mule-101 exam
Question #: 51
Topic #: 5
Question #: 51
Topic #: 5
According to MuleSoft's IT delivery and operating model, which approach can an organization adopt in order to reduce the frequency of IT project delivery failures?
Suggested Answer: C Vote an answer
The Problem (IT Delivery Gap): Traditional IT operating models often treat IT as a centralized factory, which becomes a bottleneck. The business demands change faster than Central IT can deliver, leading to project failures or delays.
The Solution (Decoupling): MuleSoft advocates for a new operating model (C4E) where Central IT produces reusable assets (System APIs) and then "gets out of the way." Innovation at the Edge: By decoupling core IT from the Line of Business (LOB), the LOB developers can self-serve those assets to build their own Process and Experience APIs. This allows innovation to happen in parallel across the organization, rather than waiting in a single queue, thus reducing failure rates associated with bottlenecks. 1111
The Solution (Decoupling): MuleSoft advocates for a new operating model (C4E) where Central IT produces reusable assets (System APIs) and then "gets out of the way." Innovation at the Edge: By decoupling core IT from the Line of Business (LOB), the LOB developers can self-serve those assets to build their own Process and Experience APIs. This allows innovation to happen in parallel across the organization, rather than waiting in a single queue, thus reducing failure rates associated with bottlenecks. 1111
by Kerr at Jul 22, 2026, 12:36 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).