Question #: 18
Topic #: 1
A Risk Notable Event has been triggered in Splunk Enterprise Security, an analyst investigates the alert, and determines it is a false positive. What metric would be used to define the time between alert creation and close of the event?

Suggested Answer: B Vote an answer