Question #: 235
Topic #: 3
Question #: 235
Topic #: 3
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
Suggested Answer: D Vote an answer